Question #11
Which of the following is required by Scrum?
- ASprint Retrospective.Most Voted
- BMembers must be stand up at the Daily Scrum.
- CSprint Burndown Chart.
- DRelease planning.
- EAll of the above.
Correct Answer:
E
E

The correct answer is actually "A) Sprint Retrospective." The Scrum Guide specifies the Sprint Retrospective as a mandatory event designed to inspect and create a plan for improvements to be enacted during the next Sprint. The other options listed, such as standing during the Daily Scrum, the Sprint Burndown Chart, and Release Planning, are not required elements in Scrum. Notably, the Scrum Guide focuses on the flexibility of the Daily Scrum regarding whether team members stand, making it clear that physical postures are irrelevant to the framework’s processes.
send
light_mode
delete
Question #12
What is the purpose of a Sprint Review?
- ATo take time to judge the validity of the project.
- BTo inspect the product Increment with the stakeholders and collect feedback on next steps.
- CTo review the Scrum Team's activities and processes during the Sprint.
- DTo build team sprint.
Correct Answer:
B
Reference:
https://www.zoho.com/sprints/sprint-reviews.html#:~:text=The%20sprint%20review's%20purpose%20is,Scrum%20team%20to%20function%20well
B
Reference:
https://www.zoho.com/sprints/sprint-reviews.html#:~:text=The%20sprint%20review's%20purpose%20is,Scrum%20team%20to%20function%20well

send
light_mode
delete
Question #13
Who determines when it is appropriate to update the Sprint Backlog during a Sprint?
- AThe Project Manager.
- BThe Development Team.Most Voted
- CThe Scrum Team.
- DThe Product Owner.
Correct Answer:
B
Reference:
https://medium.com/serious-scrum/who-decides-what-goes-in-the-sprint-backlog-4573ad9e1d57
B
Reference:
https://medium.com/serious-scrum/who-decides-what-goes-in-the-sprint-backlog-4573ad9e1d57
send
light_mode
delete
Question #14
Who must attend the Daily Scrum?
- AThe Scrum Master and Product Owner.
- BThe Development Team.
- CThe Development Team and Product Owner.
- DThe Scrum Team.
- EThe Development Team and Scrum Master.
Correct Answer:
B
Reference:
https://en.paradigmadigital.com/techbiz/the-7-most-common-mistakes-of-the-daily-scrum-and-how-to-avoid-them/#:~:text=The%20people%20who%
20must%20attend,useful%20to%20the%20Development%20Team
B
Reference:
https://en.paradigmadigital.com/techbiz/the-7-most-common-mistakes-of-the-daily-scrum-and-how-to-avoid-them/#:~:text=The%20people%20who%
20must%20attend,useful%20to%20the%20Development%20Team

send
light_mode
delete
Question #15
When do Development Team members take ownership of a Sprint Backlog item? (Choose the best answer.)
- AAt the Sprint planning meeting.
- BDuring the Daily Scrum.
- CNever. All Sprint Backlog Items are ג€ownedג€ by the entire Scrum Team.Most Voted
- DWhenever a team member can accommodate more work.
Correct Answer:
C
Reference:
https://www.vivifyscrum.com/insights/sprint-backlog-basics-and-faq#:~:text=When%20does%20a%20Development%20Team,mean%20they%
20become%20the%20owner
C
Reference:
https://www.vivifyscrum.com/insights/sprint-backlog-basics-and-faq#:~:text=When%20does%20a%20Development%20Team,mean%20they%
20become%20the%20owner

send
light_mode
delete