PMI PMI-RMP Exam Practice Questions (P. 5)
- Full Access (447 questions)
- Six months of Premium Access
- Access to one million comments
- Seamless ChatGPT Integration
- Ability to download PDF files
- Anki Flashcard files for revision
- No Captcha & No AdSense
- Advanced Exam Configuration
Question #41
As part of identifying the risk appetite of project stakeholders, the project manager must first identify the stakeholders. Which of the following inputs are used to identify project stakeholders?
- AProject charter, management reserve, enterprise environmental factors, and organizational process assets
- BProject management plan, human resource plan, enterprise environmental factors, and organizational process assets
- CProject charter, bid documents, enterprise environmental factors, and organizational process assetsMost Voted
- DProject charter, communications management plan, enterprise environmental factors, and organizational process assets
Correct Answer:
C
C
send
light_mode
delete
Question #42
After applying several risk identification techniques, the risk manager is ready to document project risks in the risk register, including risk name, risk statement, probability of occurring, and potential impact. After this information is complete, who is best suited to serve as risk owners?
- ARisk manager
- BProject sponsors
- CProject manager
- DProject team membersMost Voted
Correct Answer:
D
D
send
light_mode
delete
Question #43
Which of the following should the risk manager consider as external environmental factors when creating the risk management plan?
- AGovernment regulations, industry best practice templates, organizational standard processes, and competitor landscape
- BGovernment regulations, industry standards, conditions of the marketplace, and competitor landscape
- CGovernment regulations, risk categories, organizational standard processes, and competitor landscape
- DGovernment regulations, human resource policies and procedures, organizational standard processes, and competitor landscape
Correct Answer:
B
B
send
light_mode
delete
Question #44
Within the organizational process assets, where would the project manager find risk response effectiveness from past projects?
- AChange management plan and lessons learned
- BStakeholder register and lessons learned
- CRisk audit and lessons learned
- DRisk audit and risk matrix
Correct Answer:
C
C
send
light_mode
delete
Question #45
Which analysis method uses stratified sampling without replacement?
- ALatin Hypercube
- BMonte Carlo simulation
- CImpact analysis
- DLinear regression analysis
Correct Answer:
A
A
send
light_mode
delete
Question #46
In the country where a project is being executed, customs procedures are complex and change frequently. During the risk identification process, the project team identifies a risk related to delays in customs on substantial equipment that will likely occur. Equipment delays on this project could lead to project cancellation.
Why should a mitigation plan be developed for this risk?
Why should a mitigation plan be developed for this risk?
- AThis is a financial risk.
- BThis task is on the critical path.
- CA response plan should be developed for all risks.
- DThis is a high-priority risk.
Correct Answer:
D
D
send
light_mode
delete
Question #47
A race director is planning a marathon with US$80,000 in upfront costs that will be offset by race fees. The remainder of the funds will be donated to a national charity. State law mandates that all money paid by the participants must be refunded if the race is cancelled for any reason.
Which of the following is the best example of a risk mitigation response?
Which of the following is the best example of a risk mitigation response?
- ALet the runners know the race will be cancelled only in the event of an emergency.
- BPurchase an insurance policy covering up to US$85,000 in losses, at a cost of US$5,000, in the event the race is cancelled.
- CInform the charity that they will receive no funds should the race be cancelled.
- DCharge the runners an additional amount to cover the US$80,000.
Correct Answer:
B
B
send
light_mode
delete
Question #48
The risk manager for a construction project graphically groups project risks by the subsets of economic risk, social risk, and technical risk. Where has this information been captured?
- ARisk breakdown structure
- BRisk management plan
- CRisk register
- DRisk control plan
Correct Answer:
A
A
send
light_mode
delete
Question #49
When considering human factors and risk attitudes relative to the risk process, which approach should be used to influence the risk management process for optimal effects at the individual and group levels?
send
light_mode
delete
Question #50
What identification technique is used to help reduce the ambiguity of a risk statement?
- ADriver, risk, outcome
- BExploit, risk, accept
- CProbability, risk, impact
- DCause, risk, effect
Correct Answer:
D
D
send
light_mode
delete
All Pages