PMI PMI-RMP Exam Practice Questions (P. 2)
- Full Access (447 questions)
- Six months of Premium Access
- Access to one million comments
- Seamless ChatGPT Integration
- Ability to download PDF files
- Anki Flashcard files for revision
- No Captcha & No AdSense
- Advanced Exam Configuration
Question #11
A risk is identified and documented by the risk manager, but it is unclear how this risk can be proactively managed. In this situation, what type of reserve should be allocated for the risk?
send
light_mode
delete
Question #12
Which of the following is an effective channel for risk mitigation assistance, project risk visibility and risk escalation support?
- AProject steering committee
- BProject management office (PMO)Most Voted
- CChange control board (CCB)
- DBoard of directors
Correct Answer:
B
B
send
light_mode
delete
Question #13
The risk manager wants to determine what is to be measured, how it is to be measured, and what project outcomes are to be measured. In which of the following processes should this be established?
- AInitiating Process
- BExecuting Process
- CPlanning Process
- DMonitoring and Controlling Process
Correct Answer:
C
C
send
light_mode
delete
Question #14
Which of the following are examples of relevant data gathering tools?
- ARisk response plan and interviews
- BQuestionnaires and historical data
- CWork breakdown structure and historical data
- DWork breakdown structure and interviews
Correct Answer:
B
B
send
light_mode
delete
Question #15
The risk manager is conducting stakeholder analysis. Which technique should be used to help identify and manage expectations?
- ASWOT analysis
- BInfluence diagram
- CPower/Interest Grid
- DInteractive method
Correct Answer:
C
C
send
light_mode
delete
Question #16
What steps would be used during the qualitative risk analysis process to provide input to the risk register?
- ASelect risks characteristics, collect and analyze data, prioritize risks, categorize risks causes, document resultsMost Voted
- BInterviews, expert opinions, sponsor inputs, risk manager review, prioritize risks, and document results
- CInterviews, expert opinions, risk manager review, prioritize risks, and document results
- DSelect risks characteristics, collect and analyze data, prioritize risks, discuss action plans for major risks, document results
Correct Answer:
C
C
send
light_mode
delete
Question #17
A project manager is hired as a consultant by the executive sponsor to manage a major change program that has experienced two past failures. The current executive sponsor believes the project is in good shape based on feedback from the last project manager and reports this to senior executive management. The executive sponsor believes there were no major risks threatening the time, budget, or quality of the project. In the first week of risk analysis, the project manager concludes the project timeline is unrealistic and is three months behind schedule. The organization's risk appetite is low.
What is the first step that should be taken?
What is the first step that should be taken?
- AReview the project schedule and recommend fast tracking the schedule and/or crashing the critical path.
- BDiscuss the project schedule with the executive sponsor and agree on a strategy for updating the risk management plan and risk response plans.Most Voted
- CUpdate existing risk response plans and include more resources to get the project back on track.
- DImmediately call a steering committee meeting, report the project status, and suggest project scope reductions to save time.
Correct Answer:
B
B
send
light_mode
delete
Question #18
During what process should a project manager assign a risk owner?
- APlan Risk Responses
- BPlan Risk Management
- CMonitor Risks
- DIdentify RisksMost Voted
Correct Answer:
A
A
send
light_mode
delete
Question #19
A risk manager wants to determine which risks are going to have the highest impact on a project. Which of the following techniques should the risk manager use?
- AAssumptions analysis
- BSensitivity analysisMost Voted
- CRoot cause analysis
- DPrioritization matrices
Correct Answer:
B
B
send
light_mode
delete
Question #20
Critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. How could the situation be improved for the future?
- ACross train others to reduce the SME workload.Most Voted
- BIntroduce scope reductions to limit the reliance on SMEs.
- CReplace the SME with resources, who are responsible for receiving output from the SME on their deliverables.
- DExtend the project schedule timeline to accommodate availability of the SME.
Correct Answer:
B
B
send
light_mode
delete
All Pages