PMI PMI-RMP Exam Practice Questions (P. 3)
- Full Access (447 questions)
- Six months of Premium Access
- Access to one million comments
- Seamless ChatGPT Integration
- Ability to download PDF files
- Anki Flashcard files for revision
- No Captcha & No AdSense
- Advanced Exam Configuration
Question #21
In what way can the risk manager determine when poor risk planning techniques are influencing the scope, schedule, quality, and/or budget of the project?
- AEvaluate the results of the Monte Carlo analysis
- BDocument and periodically update project risk information
- CMonitor project metrics and performance information
- DUpdate the risk management plan
Correct Answer:
C
C
send
light_mode
delete
Question #22
The company board is concerned about potential legal action from a high-risk project What technique can be used to justify risk response decisions taken on this project?
- AInterviews
- BNominal group technique
- CBrainstorming
- DDecision tree analysis
Correct Answer:
D
D
send
light_mode
delete
Question #23
The project manager generates a monthly risk report for key stakeholders which documents high and medium risk items only. Where would the project manager find the list of recipients for the report?
- ACommunications management plan
- BRisk management plan
- CRisk register
- DProject charter
Correct Answer:
A
A
send
light_mode
delete
Question #24
A CEO wants to reduce costs in the time spent for risk management activities. What step did the risk manager fail to perform?
- AAssigning the CEO as a risk owner
- BPreventing all issues from occurring
- CProperly communicating the risk management activities and their outcomesMost Voted
- DExplaining the purpose of the management reserve
Correct Answer:
B
B
send
light_mode
delete
Question #25
A risk on the risk register is triggered. This triggered risk costs US$200,000 to mitigate and will overwhelm the project, causing it to fail if not mitigated. The project manager identifies that there is US$200,000 left in the management reserve.
From which of the following sources should the funds be drawn to cover the risk mitigation?
From which of the following sources should the funds be drawn to cover the risk mitigation?
- AOrganization management reserve
- BUnplanned risk reserve
- CContingency reserveMost Voted
- DManagement reserve
Correct Answer:
C
C
send
light_mode
delete
Question #26
Which tool can the project risk manager utilize to help identify and assess project risks?
- ARisk audit
- BRisk surveys
- CRisk manager interviews
- DRisk sensitivity surveys
Correct Answer:
B
B
send
light_mode
delete
Question #27
The project manager is unable to obtain a global consensus of competing subject matter experts and stakeholders on the project scope. This has caused a one- month delay.
What should the project manager do next to reduce further delay?
What should the project manager do next to reduce further delay?
- AInitiate a scope change request.
- BSchedule a project kick-off meeting.
- CSchedule a stakeholder meeting.Most Voted
- DEngage the project sponsor/portfolio manager.
Correct Answer:
A
A
send
light_mode
delete
Question #28
A risk is identified early in the project. After six months, it is determined that the risk does not apply to this particular project.
How should the risk be handled by the risk manager?
How should the risk be handled by the risk manager?
- AIgnore the risk and concentrate only on the pertinent risks.
- BRemove the risk from the risk register and inform the project manager that it is no longer valid.
- CClose the risk during the next risk board meeting and keep it in the risk register.Most Voted
- DConduct a risk analysis to determine how an inappropriate risk was formally accepted.
Correct Answer:
B
B
send
light_mode
delete
Question #29
Who is ultimately responsible for monitoring a risk that is about to exceed its risk threshold?
- AAny project stakeholder
- BProject management office
- CSenior manager
- DRisk action owner
Correct Answer:
D
D
send
light_mode
delete
Question #30
The sponsor hires a program manager as a consultant to evaluate a change program currently underway. The leading program manager tells the consultant that the program, currently in the execution phase, is in good standing, and detailed plans are available for review. The consultant reviews the project documentation and talks to the stakeholders, finding the opposite to be true. The project must be in recovery mode to get it back on track, and it is still in the planning phase.
There is low morale among the team members, the meetings are poorly managed, the detailed schedule has gaps, the risk register has not been updated for months, communications and detailed resource plans do not exist, and contract negotiations with a key vendor are behind schedule for critical deliverables.
What is the first course of action the program manager should take based on the current state?
There is low morale among the team members, the meetings are poorly managed, the detailed schedule has gaps, the risk register has not been updated for months, communications and detailed resource plans do not exist, and contract negotiations with a key vendor are behind schedule for critical deliverables.
What is the first course of action the program manager should take based on the current state?
- ACancel or put the project on hold, and hire a new program manager.
- BAssess the risk management plan and adjust it accordingly to accommodate the gaps.
- CContinue the project and create the project documentation that is missing.
- DMeet with the project sponsor to report current findings, review current risk management plan and develop a corrective course of action.
Correct Answer:
D
D
send
light_mode
delete
All Pages