Question #41
A milestone task on the critical path has been completed.
Which of the following should the project manager notify?
Which of the following should the project manager notify?
- AOwner of predecessor task
- BProject team
- CProject sponsorMost Voted
- DProject steering committee
Correct Answer:
C
C
send
light_mode
delete
Question #42
During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project.
Which of the following actions should the project manager take?
Which of the following actions should the project manager take?
- AAlert the project sponsor of the situation.Most Voted
- BContact the customer and request more funding.
- CAnnounce the project will end early due to lack of funds.
- DAttempt to save money in downstream activities.
Correct Answer:
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 233
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 233
send
light_mode
delete
Question #43
Which of the following is the primary purpose of an MOA or an MOU?
- AState expectations of all signatory parties to reduce potential misunderstandings.Most Voted
- BFacilitate potential legal action and resulting remediation if one of the signatory parties violates any terms.
- CEnumerate a detailed code of conduct for all employees, contractors, and subcontractors participating in the program.
- DProvide transparency to competitors regarding all signatory parties.
Correct Answer:
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 303
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 303
send
light_mode
delete
Question #44
Two team members have concluded that documentation is not required due to the size of the current project. The project manager has encouraged them to align strictly within the process.
Which of the following conflict resolution techniques has the project manager utilized?
Which of the following conflict resolution techniques has the project manager utilized?
- ASmoothing
- BForcing
- CCompromising
- DAvoiding
Correct Answer:
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 200
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 200
send
light_mode
delete
Question #45
The client accepts the critical design review.
Which of the following meetings should be held to move to the NEXT step in the project?
Which of the following meetings should be held to move to the NEXT step in the project?
- AExecution
- BKickoff
- CClosure
- DPlanning
Correct Answer:
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 112
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 112
send
light_mode
delete
Question #46
A project manager is working on the project charter.
Which of the following phases does this describe?
Which of the following phases does this describe?
- AInitiation
- BPlanning
- CExecution
- DClosing
Correct Answer:
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 107
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 107
send
light_mode
delete
Question #47
A project in the execution phase is over budget, and tasks on the critical path are on schedule.
Which of the following should the project manager do NEXT?
Which of the following should the project manager do NEXT?
- AUpdate the project management plan.
- BIssue a change request.Most Voted
- CRevise the project charter.
- DEvaluate the impact to the baseline.
Correct Answer:
D
D
send
light_mode
delete
Question #48
Several team members report that meeting objectives are not being met.
Which of the following documents would a project manager create to make team meetings more effective? (Choose two.)
Which of the following documents would a project manager create to make team meetings more effective? (Choose two.)
- ACreate an SOW prior to each meeting and adhere to it.
- BCreate a meeting agenda prior to each meeting and adhere to it.
- CCreate a lessons learned list prior to each meeting and adhere to it.
- DCreate a project charter prior to each meeting and adhere to it.
- ECreate an action item list during the meeting and adhere to it.
- FCreate a corrective action plan prior to each meeting and adhere to it.
- GCreate a WBS prior to each meeting and adhere to it.
Correct Answer:
BE
BE
send
light_mode
delete
Question #49
Which of the following documents should be used to provide high-level reporting to key stakeholders?
- ADashboardMost Voted
- BCommunication plan
- CStatement of work
- DProject charter
Correct Answer:
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 325
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 325
send
light_mode
delete
Question #50
A new project charter is being drafted.
Which of the following would be the BEST source for the high-level project requirements?
Which of the following would be the BEST source for the high-level project requirements?
- ASponsor
- BProject manager
- CProject management office
- DProject team
Correct Answer:
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 108
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 108