Question #1
A project manager is attempting to establish the proper sequencing and duration of project activities.
Which of the following would be the MOST beneficial?
Which of the following would be the MOST beneficial?
- ANetwork diagram
- BIshikawa diagram
- CWBS
- DGantt chart
Correct Answer:
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 160
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 160
send
light_mode
delete
Question #2
Which of the following are characteristics of a project? (Choose two.)
- AOngoing
- BTemporaryMost Voted
- CStart and finishMost Voted
- DAchieving a goal
- EConsisting of milestones
- FRestricting the budget
Correct Answer:
BC
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 27
BC
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 27
send
light_mode
delete
Question #3
A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services.
Which of the following documents will the company MOST likely release FIRST?
Which of the following documents will the company MOST likely release FIRST?
- ARFO
- BRFI
- CRFP
- DRFQ
Correct Answer:
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 300
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 300
send
light_mode
delete
Question #4
The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation.
Which of the following should the project manager bring to the meeting to support this recommendation? (Choose two.)
Which of the following should the project manager bring to the meeting to support this recommendation? (Choose two.)
- AThe issue log to show why the vendor should be replaced.Most Voted
- BThe team action items to show why the vendor should be replaced.
- CThe scope statement to show why the vendor should be replaced.
- DA procurement plan to show why the vendor should be replaced.
- EA change management plan to have the vendor replaced.Most Voted
Correct Answer:
AE
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 291, p. 327
AE
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 291, p. 327
send
light_mode
delete
Question #5
A project manager is creating the WBS.
In which of the following phases is the project?
In which of the following phases is the project?
- AInitiation
- BPlanningMost Voted
- CExecution
- DClosing
Correct Answer:
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 139
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 139
send
light_mode
delete
Question #6
Which of the following is a characteristics of a matrix organization?
- AAuthority lies solely with the project manager.
- BAuthority is directed by the project architect.
- CAuthority is shared between the project manager and project coordinator.
- DAuthority is shared between functional and project managers.Most Voted
Correct Answer:
D
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 56
D
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 56
send
light_mode
delete
Question #7
A WBS is being developed for a project.
Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
- AProject team membersMost Voted
- BProject sponsor
- CProject manager
- DProject scheduler
Correct Answer:
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 82
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 82
send
light_mode
delete
Question #8
A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints.
Which of the following documents should the project manager use to obtain this information?
Which of the following documents should the project manager use to obtain this information?
- AProject schedule
- BBalanced scorecard
- CIssue log
- DStatus reportMost Voted
Correct Answer:
D
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 328
D
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 328
send
light_mode
delete
Question #9
A stakeholder is unaware of a project's status.
Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)
Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)
- AStatus reportMost Voted
- BOrganizational chart
- CRACI matrix
- DMeeting minutes
- ECommunication planMost Voted
Correct Answer:
AD
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261
AD
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261
send
light_mode
delete
Question #10
There are four parallel paths on a network diagram. The summary duration of each path is below:
A, C, G: 10 weeks -
A, B, F: 8 weeks -
D, E, H: 12 weeks -
D, B, F: 7 weeks -
Which of the following tasks are on the critical path?
A, C, G: 10 weeks -
A, B, F: 8 weeks -
D, E, H: 12 weeks -
D, B, F: 7 weeks -
Which of the following tasks are on the critical path?
- AA, C, G
- BA, B, F
- CD, E, HMost Voted
- DD, B, F
Correct Answer:
C
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 175
C
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 175