Question #21
During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project.
Which of the following documents would contain these items?
Which of the following documents would contain these items?
- ABusiness caseMost Voted
- BRequirements document
- CProject timeline
- DTask plan
Correct Answer:
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 138
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 138
send
light_mode
delete
Question #22
A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave.
Which of the following should a project manager update to document this information?
Which of the following should a project manager update to document this information?
- AA list of realized risks
- BA list of decomposed activities
- CA sequenced list of project tasks
- DA document describing agreed-upon communication methods
Correct Answer:
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 240
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 240
send
light_mode
delete
Question #23
The executive sponsor asks a project manager to summarize the following for a project:
1. Final capital expenditures.
2. Anticipated cost of new employee resources to support the solution.
3. Maintenance estimates.
Which of the following information should the project manager provide?
1. Final capital expenditures.
2. Anticipated cost of new employee resources to support the solution.
3. Maintenance estimates.
Which of the following information should the project manager provide?
- ACost baseline
- BBurn rate
- CCost variance report
- DTotal project costMost Voted
Correct Answer:
A
A
send
light_mode
delete
Question #24
Which of the following defines a group of projects that work together to achieve a common goal?
- AProduct
- BPortfolio
- CProgram
- DProject plan
Correct Answer:
C
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 71
C
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 71
send
light_mode
delete
Question #25
A company hires an outside vendor to provide 24/7 support.
Which of the following documents would determine the contractual obligations?
Which of the following documents would determine the contractual obligations?
- APO
- BSLA
- CLOI
- DMOU
Correct Answer:
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 303
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 303
send
light_mode
delete
Question #26
A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time.
Which of the following techniques is MOST likely to be used to complete the project on time?
Which of the following techniques is MOST likely to be used to complete the project on time?
- AThrottling
- BCrashing
- CResource leveling
- DResource smoothing
Correct Answer:
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 170
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 170
send
light_mode
delete
Question #27
A project manager is unsure if the quality of a deliverable from a SME meets specifications.
Which of the following is the BEST way for the project manager to address the issue?
Which of the following is the BEST way for the project manager to address the issue?
- AConduct a face-to-face or telephone meeting with the team member.
- BSend an email outlining the concerns to the team member.
- CSend a project team meeting to obtain feedback from everyone.
- DPost the issue on the wiki page for input from stakeholders.
Correct Answer:
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261
send
light_mode
delete
Question #28
Which of the following is a key aspect of the Agile project management methodology?
- ATest-driven
- BDaily standup meetings
- CShort project durations
- DDefined list of requirements
Correct Answer:
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 286
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 286
send
light_mode
delete
Question #29
A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule.
Which of the following is the FIRST step the project manager should take?
Which of the following is the FIRST step the project manager should take?
- AAssess the risk register's new items.
- BReview the task start and finish dates.
- CObtain additional resources.
- DAnalyze the assigned hours.
Correct Answer:
A
A
send
light_mode
delete
Question #30
A project manager is managing a transactional project. One of the key team members is having difficulties understanding the client requirements.
Which of the following actions would be BEST for the project manager to take?
Which of the following actions would be BEST for the project manager to take?
- AAsk the client to provide additional language resources to the team.
- BPurchase a language translation program.
- CHire a translator to help the key team member
- DAsk the client to provide requirements in the native language of the team.
Correct Answer:
D