Question #41
Which of the following statements would NOT be included in the Project Product Description?
- APurpose of the product
- BComposition
- CProject level tolerances
- DQuality criteriaMost Voted
Correct Answer:
D
D
send
light_mode
delete
Question #42
In the PRINCE2 Quality review technique, who would most likely carry out the role of administrator:
- AProject manager
- BProject supportMost Voted
- CTeam Manager
- DProject Assurance
Correct Answer:
B
B
send
light_mode
delete
Question #43
Which role is responsible for providing the customer's quality expectations and acceptance criteria for the project?
- AExecutive
- BCorporate or Programme Management
- CSenior UserMost Voted
- DProject Assurance
Correct Answer:
C
C
send
light_mode
delete
Question #44
Which management product defines the detailed nature, purpose and function of a product?
- APlan
- BQuality Register
- CProject Product Description
- DProduct Description
Correct Answer:
D
D
send
light_mode
delete
Question #45
DRAG DROP -
QUALITY -
Here are three actions related to managing quality on the Health and Safety Training Project.
Which role (A-F) should be responsible for each action?
Choose only one role for each action. Each role can be used once, more than once, or not at all.
Select and Place:

QUALITY -
Here are three actions related to managing quality on the Health and Safety Training Project.
Which role (A-F) should be responsible for each action?
Choose only one role for each action. Each role can be used once, more than once, or not at all.
Select and Place:

send
light_mode
delete
Question #46
PRINCE2 proposes 3 levels of Plan, which are they?
- AInitiation, Project and Stage Plans
- BProject, Stage and Exception Plans
- CInitiation, Project and Benefit Review Plans
- DProject, Stage and Team Plans
Correct Answer:
D
D
send
light_mode
delete
Question #47
Having completed designing the plan, in which order should the next steps take place to produce a plan?
1. Prepare Estimates
2. Define and analyze Products
3. Prepare the schedule
4. Identify activities and dependencies
1. Prepare Estimates
2. Define and analyze Products
3. Prepare the schedule
4. Identify activities and dependencies
send
light_mode
delete
Question #48
Product based planning focuses on which of the following:
1. Creating product descriptions
2. Identifying activities
3. Creating a Product hierarchy
4. Creating a Product sequence
1. Creating product descriptions
2. Identifying activities
3. Creating a Product hierarchy
4. Creating a Product sequence
send
light_mode
delete
Question #49
Who sets the tolerances for a work package?
- AThe project board
- BThe project manager
- CThe team manager
- DCorporate or programme management
Correct Answer:
B
B
send
light_mode
delete
Question #50
Which of the following is not part of the composition of a Plan?
- APre-requites
- BAssumptions
- CQuality responsibilitiesMost Voted
- DProduct descriptions
Correct Answer:
C
C
send
light_mode
delete