Question #1
Which of the following statements describes an outcome?
- AAny of the projects specialist products
- BA result of the change derived from using the project's products
- CA measurable improvement resulting from a change
- DSomething perceived as advantages by a stakeholder
Correct Answer:
B
B
send
light_mode
delete
Question #2
Which of the following should NOT be included in the business case?
send
light_mode
delete
Question #3
When considering the business options in the business case, which of these is NOT an option?
send
light_mode
delete
Question #4
Which of the following statements is TRUE with regard to expected benefits?
- AThey cannot be assigned
- BThey don't need to follow corporate objectives
- CThey should be measurable
- DTolerances cannot be set against expected benefits
Correct Answer:
C
C
send
light_mode
delete
Question #5
Who is responsible for ensuring that the value-for-money solution is constantly reassessed?
- ABusiness Assurance
- BSenior User
- CCorporate or Programme Management
- DReject Support
Correct Answer:
A
A
send
light_mode
delete
Question #6
Which of the following activities is the Executive responsible for?
- AEnsure the desired outcome of the project is specified
- BResponsible for the benefits review plan
- CAssess and update the Business Case at the end of each stage
- DResponsible for the Benefits Review Plan post project
Correct Answer:
B
B
send
light_mode
delete
Question #7
DRAG DROP -
BUSINESS CASE -
Here are three statements from the business case for the Health and Safety Project.
Under which heading in the business case (A-F) should they be recorded?
Choose only one heading for each statement. Each heading can be used once, more than once, or not at all.
Select and Place:

BUSINESS CASE -
Here are three statements from the business case for the Health and Safety Project.
Under which heading in the business case (A-F) should they be recorded?
Choose only one heading for each statement. Each heading can be used once, more than once, or not at all.
Select and Place:

send
light_mode
delete
Question #8
The executive has asked the project manager to plan for the 'e-learning course' to be used as soon as it is accredited. The aim is to start selling the 'e-learning course' while the remainder of the outputs relating to classroom-based delivery are finished. The sales of the 'e-learning course' will be entered into the business case.
Why is the executive's decision to deliver the benefits early appropriate for managing the business case?
Why is the executive's decision to deliver the benefits early appropriate for managing the business case?
- ABecause organizations with mature project management often include the early justification for the project in the business case.
- BBecause the outputs being delivered incrementally will be beneficial and will allow the business case to be justified.Most Voted
- CBecause one of the PRINCE2 principles is that a project should focus on products to deliver the outputs early.
- DBecause the business case should be updated after every increment of the 'e-learning course'.
Correct Answer:
C
C
send
light_mode
delete
Question #9
During stage 3, the project scope was extended to include a practice test for learners to take during the training course. The cost of this test will be included in the cost of the course.
The change to project scope was approved and the cost of ֲ£2,500 was paid for from the change budget. The project manager documented an increase of ֲ£2,500 in the project budget in the business case.
Is this an appropriate action, and why?
The change to project scope was approved and the cost of ֲ£2,500 was paid for from the change budget. The project manager documented an increase of ֲ£2,500 in the project budget in the business case.
Is this an appropriate action, and why?
- AYes, because the justification for the project should be recalculated based on the revised project budget.
- BYes, because the project manager determines which costs need to be updated at the end of each stage
- CNo, because the use of the change budget means that the project budget does not need to be increased.Most Voted
- DNo, because changes to operational costs post-project should have been included in the business case.
Correct Answer:
B
B
send
light_mode
delete
Question #10
When updating the project plan as part of Managing a stage boundary, what else might be updated?
- AException Plan
- BProject Management team
- CBusiness CaseMost Voted
- DProject Initiation Documentation
Correct Answer:
A
A
send
light_mode
delete