Question #11
Which of the following management products ARE updated as part of Managing a stage boundary?
1. Business Case
2. Benefits Review Plan
3. Configuration Item Records
4. Project Brief
1. Business Case
2. Benefits Review Plan
3. Configuration Item Records
4. Project Brief
send
light_mode
delete
Question #12
Which of the following activities could trigger the production of an exception plan?
- AReview Stage status
- BGiving ad hoc direction
- CEscalating a project issue
- DReport stage endMost Voted
Correct Answer:
B
B
send
light_mode
delete
Question #13
Which of the following statements is FALSE regarding the Continued Business Justification?
- AThe justification for the project must remain the same throughout the project.Most Voted
- BThe justification for the project should remain vabd.
- CThe justification for the project may change.
- DIf the project is no longer justified it should be stopped.
Correct Answer:
B
B
send
light_mode
delete
Question #14
Which of the following activities is NOT an action of preparing for planned closure?
- AUpdate the project plan with actual
- BUpdate the Project Management Team
- CRequest a product status account
- DConfirm project has delivered what is defined in Project Product Description
Correct Answer:
B
B
send
light_mode
delete
Question #15
Which principle is supported by the activity Evaluate the Project?
- AContinued Business Justification
- BDefined roles and responsibilities
- CLearn from experienceMost Voted
- DManage by stages
Correct Answer:
C
C
send
light_mode
delete
Question #16
HOTSPOT -
The Calendar project was delivered as originally planned, and Is now preparing for planned closure.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.
Hot Area:

The Calendar project was delivered as originally planned, and Is now preparing for planned closure.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.
Hot Area:

send
light_mode
delete
Question #17
The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?
- AScope, People & Resources, Benefit
- BScope, Risk, Product
- CRisk, Benefit, Product
- DScope, Risk, Benefit
Correct Answer:
D
D
send
light_mode
delete
Question #18
MANAGING A STAGE BOUNDARY -
The project is approaching the end of stage 3 and the pilot courses have been planned. The project manager is now undertaking the 'managing a stage boundary' process.
Which action should the project manager undertake as part of the 'update the business case' activity?
The project is approaching the end of stage 3 and the pilot courses have been planned. The project manager is now undertaking the 'managing a stage boundary' process.
Which action should the project manager undertake as part of the 'update the business case' activity?
- AIdentify the dependencies between the activities required to run the 'delivered pilot courses' during stage 4.
- BRevise the overall plan and resources to complete the project, based on actuals from the stage 3 plan.Most Voted
- CReview the performance of the external suppliers who worked on delivery of the 'e-learning course' during stage 3.
- DRe-plan when the number of learners using the pilot course, and their increased knowledge, will be measured during stage 4.
Correct Answer:
A
A
send
light_mode
delete
Question #19
The project is approaching the end of stage 3, and stage 4 is being planned as part of the 'managing a stage boundary' process.
Which action should the project manager carry out as part of the 'update the project plan' activity?
Which action should the project manager carry out as part of the 'update the project plan' activity?
- AInclude the actual time and cost of the work to prepare the 'marketing materials' in the project plan.
- BEnsure that the team manager for the work package 'delivered pilot courses' is included as a resource.
- CUpdate the project's business case to show any new key risks that have been identified.Most Voted
- DInclude the tolerances for the work package 'delivered pilot courses' in the project plan.
Correct Answer:
A
Reference:
https://www.prince2primer.com/prince2-2017-update-project-plan-business-case/
A
Reference:
https://www.prince2primer.com/prince2-2017-update-project-plan-business-case/
send
light_mode
delete
Question #20
After preparing the stage 3 plan, the project manager left the company. The project board has decided that, as the stage plan has been agreed, it will not appoint a project manager for stage 3. The team managers will report directly to the project board and will prepare highlight reports instead of checkpoint reports.
Is this an appropriate tailoring of the roles in the 'managing a stage boundary' process?
Is this an appropriate tailoring of the roles in the 'managing a stage boundary' process?
- AYes, because work may be delegated to those with the necessary skills, such as a team manager.Most Voted
- BYes, because the team managers should have the information required to prepare highlight reports.
- CNo, because the reporting in the 'controlling a stage' process should not be changed.
- DNo, because the team managers should not share the responsibilities of the project manager.
Correct Answer:
D
Reference:
https://www.prince2primer.com/the-project-manager-role/
D
Reference:
https://www.prince2primer.com/the-project-manager-role/