Question #41
Which is a purpose of the Managing Product Delivery process?
- AEnable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package
- BProvide a controlled link between the Project Manager and the Team Manager(s)Most Voted
- CEnable the Project Board to request updates to the current Team Plan
- DEstablish solid foundations for the project
Correct Answer:
B
B
send
light_mode
delete
Question #42
From whom does a Team Manager obtain approval for a completed product?
- AProject Manager
- BProject Support
- CThe authority defined in the Product Description
- DSenior Supplier
Correct Answer:
C
C
send
light_mode
delete
Question #43
Which is an objective of the 'managing product delivery' process?
- ATo authorize the work package allocated to the team
- BTo raise exception reports when tolerance is exceeded
- CTo ensure that delivered products match expectationsMost Voted
- DTo record any lessons to help later management stages
Correct Answer:
A
The objective of the Managing Product Delivery process is to ensure that:
Products assigned to the team are authorized and agreed upon.
Reference:
https://prince2.wiki/processes/managing-product-delivery/
A
The objective of the Managing Product Delivery process is to ensure that:
Products assigned to the team are authorized and agreed upon.
Reference:
https://prince2.wiki/processes/managing-product-delivery/
send
light_mode
delete
Question #44
What process aims to ensure accurate progress information is provided to the Project Manager?
- AStarting up a Project
- BManaging a Stage Boundary
- CManaging Product Delivery
- DDirecting a Project
Correct Answer:
C
C
send
light_mode
delete
Question #45
Which process covers the work done by external suppliers who may NOT be using PRINCE2?
- AClosing a Project
- BManaging a Stage Boundary
- CManaging Product Delivery
- DDirecting a Project
Correct Answer:
C
C
send
light_mode
delete
Question #46
Which two roles are linked by the Managing Product Delivery process?
- ACorporate or programme management and Project Board
- BProject Board and Project Manager
- CProject Manager and Team Manager
- DTeam Manager and external supplier
Correct Answer:
C
C
send
light_mode
delete
Question #47
What is the collective name for individuals or groups who may be affected by a project?
send
light_mode
delete
Question #48
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
- ACreate a separate Project Board to manage the supplier elements of the project
- BCreate multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.
- CCreate user and supplier groups
- DAppoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board
Correct Answer:
C
C
send
light_mode
delete
Question #49
When should the Project Board refer to corporate or programme management for a decision?
- AThe stage requires resources
- BIt is forecast that project level tolerance will be exceededMost Voted
- CThe Senior Supplier or Senior User needs to be changed
- DAny request for change needs to be approved
Correct Answer:
B
B
send
light_mode
delete
Question #50
Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage
Report to external interested parties.
Report to external interested parties.
- AStage Plan
- BCommunication Management Strategy
- CFollow-on action recommendations
- DQuality Management Strategy
Correct Answer:
B