Question #21
Which is a purpose of the Closing a Project process?
- AAuthorize the final stage of the project
- BConfirm that all benefits defined in the Business Case have been achieved
- CRecognize whether objectives set out in the original Project Initiation Documentation have been achieved
- DDelegate day-to-day management of the end of the project to the Project Manager
Correct Answer:
C
C
send
light_mode
delete
Question #22
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
- AOff-specifications
- BFollow-on action recommendations
- CIssue Register
- DRisk Register
Correct Answer:
B
B
send
light_mode
delete
Question #23
Which is an objective of the 'closing a project' process?
- ATo provide corporate management with an interface to the project
- BTo ensure the project's delivery will be within set tolerances
- CTo seek approval to replace the project or stage plan
- DTo assess the benefits that have already been realizedMost Voted
Correct Answer:
B
Reference:
https://prince2.wiki/processes/closing-a-project/
B
Reference:
https://prince2.wiki/processes/closing-a-project/
send
light_mode
delete
Question #24
Which is a purpose of the Controlling a Stage process?
- AProduce a Team Plan for the work to be assigned to a Team Manager
- BSelect and implement actions that will resolve deviations from a plan within toleranceMost Voted
- CObtain approvals for products delivered in a Work Package
- DUpdate a Project Plan to incorporate the actuals from a Stage Plan
Correct Answer:
B
B
send
light_mode
delete
Question #25
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
- ADirecting a Project
- BManaging a Stage Boundary
- CControlling a Stage
- DStarting up a Project
Correct Answer:
C
C
send
light_mode
delete
Question #26
Which process is triggered towards the end of the final stage when all the assigned work has been completed?
- AManaging a Stage Boundary
- BManaging Product Delivery
- CClosing a Project
- DControlling a Stage
Correct Answer:
C
C
send
light_mode
delete
Question #27
Which is a purpose of the Controlling a Stage process?
- AAssign work to be done and take corrective action to ensure that the stage remains within tolerance
- BProvide a fixed reference point at which acceptance for the project product is confirmed
- CEnable the Project Board to be provided with sufficient information to authorize the next stage
- DEnable the organization to understand the work that needs to be done to deliver the project's products
Correct Answer:
A
A
send
light_mode
delete
Question #28
What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?
- ADirecting a Project
- BControlling a Stage
- CManaging a Stage Boundary
- DManaging Product Delivery
Correct Answer:
B
B
send
light_mode
delete
Question #29
In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?
send
light_mode
delete
Question #30
Which is a purpose of the 'directing a project' process?
- ATo answer the question: Do we have a viable and worthwhile project?
- BTo coordinate an area of work delivering the project product's components
- CTo delegate day to day management of the project to the project manager
- DTo provide a fixed point to confirm acceptance of the project product
Correct Answer:
C
The purpose of the Directing a Project process is to enable the project board to be accountable for the project's success by making key decisions and exercising overall control while delegating day-to-day management of the project to the project manager.
Reference:
https://publications.axelos.com/prince2agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_112#:~:text=The%20purpose%20of%20the%
20Directing,project%20to%20the%20project%20manager
.
C
The purpose of the Directing a Project process is to enable the project board to be accountable for the project's success by making key decisions and exercising overall control while delegating day-to-day management of the project to the project manager.
Reference:
https://publications.axelos.com/prince2agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_112#:~:text=The%20purpose%20of%20the%
20Directing,project%20to%20the%20project%20manager
.
send
light_mode
delete