Question #31
Why is tailoring required in a project?
- ABecause a one-size-fits-all approach avoids complications and saves time
- BBecause every project is unique and not every tool, technique, input, or output identified in the PMBOK Guide is requiredMost Voted
- CBecause tailoring allows us to identify the techniques, procedures, and system practices used by those in the project
- DProject managers should apply every process in the PMBOK Guide to the project, so tailoring is not required
Correct Answer:
B
B
send
light_mode
delete
Question #32
Company A has just been notified about a new legal requirement for its business operations. What is the classification of this item?
- AInternal enterprise environmental factor
- BRisk register database
- CExternal enterprise environmental factorMost Voted
- DOrganizational process asset
Correct Answer:
C
C
send
light_mode
delete
Question #33
Which of the following documents are created as part of Project Integration Management?
- AProject charter and project management planMost Voted
- BCommunications management plan and scope management plan
- CQuality management plan and risk management plan
- DProject scope statement and communications management plan
Correct Answer:
A
A
send
light_mode
delete
Question #34
A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages.
Which technique is the project manager using?
Which technique is the project manager using?
- AThree-point estimating
- BParametric estimating
- CBottom-up estimatingMost Voted
- DData analysis
Correct Answer:
C
C
send
light_mode
delete
Question #35
A project manager is updating their CV or resume and realizes that they need to improve skills related to expertise in the industry and organizational knowledge.
Which dimension of PMI's Talent Triangle best relates to this need to improve?
Which dimension of PMI's Talent Triangle best relates to this need to improve?
- AStrategic and business management skillsMost Voted
- BLeadership skills
- CTechnical project management
- DOrganizational management
Correct Answer:
A
A
send
light_mode
delete
Question #36
Which project documents can determine the budget?
- AProcurement documents, contracts, requirements documentation, and basis of estimates
- BBasis of estimates, cost estimates, project schedule, and risk registerMost Voted
- CBusiness case, project charter, statement of work, and cost estimates
- DScope baseline, resource management plan, activity list, and assumption log
Correct Answer:
B
B
send
light_mode
delete
Question #37
When managing costs in an agile environment, what should a project manager consider?
- ALightweight estimation methods can be used as changes ariseMost Voted
- BAgile environments make cost aggregation more difficult
- CAgile environments make projects more costly and uncertain
- DDetailed cost calculations benefit from frequent changes
Correct Answer:
A
A
send
light_mode
delete
Question #38
Which statement describes the Monitor Communications process?
- AEvaluates the differences between the communications management plan and the reality of communications in a project
- BEnsures that the information needs of the project and the stakeholders are metMost Voted
- CEnsures that project information is created, collected, and distributed in a timely and appropriate manner
- DDevelops an appropriate and plan for communication of project activities
Correct Answer:
B
B
send
light_mode
delete
Question #39
Which tasks should a project manager accomplish in order to manage project scope correctly?
- ADefine, Validate, and Control Scope; Control Schedule; Control Costs and Manage Stakeholder Engagement.
- BCollect Requirements, Define Scope, Create WBS, Develop Schedule, and Manage Stakeholder Engagement.
- CPlan Scope Management; Collect Requirements; Define, Validate, and Control Scope; and Create WBS.Most Voted
- DDefine, Validate, and Control Scope; Control Costs; Manage Stakeholder Engagement; and keep budget under control.
Correct Answer:
C
C
send
light_mode
delete
Question #40
In a preliminary meeting for a project, team members decide to execute the project with agile methodology. A finance team member wants to know how project cost will be determined at this early stage.
How will the project team determine project cost?
How will the project team determine project cost?
- AUse a lightweight cost estimation due to the nature of agile projectsMost Voted
- BUse a detailed cost estimation for agile projects
- CRetrieve a budget from a previous project and create a baseline for this project based on it
- DUse a detailed work breakdown structure (WBS) to get cost estimation
Correct Answer:
A
A