Question #11
DRAG DROP -
You are project manager in your companys PMO. You have permission to manage the Enterprise Global view in Microsoft PPM. Your organization works with many large multiyear projects often managed by more than one project manager.
You need to provide an Enterprise Global view that displays the fields necessary for your colleagues to control whether a task is published, who will be responsible for sending the task updates for the task, and who is responsible for approving updates from resources.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Select and Place:

You are project manager in your companys PMO. You have permission to manage the Enterprise Global view in Microsoft PPM. Your organization works with many large multiyear projects often managed by more than one project manager.
You need to provide an Enterprise Global view that displays the fields necessary for your colleagues to control whether a task is published, who will be responsible for sending the task updates for the task, and who is responsible for approving updates from resources.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Select and Place:

send
light_mode
delete
Question #12
HOTSPOT -
Your organization uses Microsoft PPM and Power BI to manage projects. You create status reports for projects by using Microsoft Excel files and Power BI
Desktop. You plan to combine several specific reports into a single Power BI dashboard.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
Hot Area:

Your organization uses Microsoft PPM and Power BI to manage projects. You create status reports for projects by using Microsoft Excel files and Power BI
Desktop. You plan to combine several specific reports into a single Power BI dashboard.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
Hot Area:

send
light_mode
delete
Question #13
You are managing an e-commerce portal development project by using Microsoft PPM.
In order to communicate the status of your project to your stakeholders, you want to create a real time project status report using Microsoft Excel in Office Online
Services.
You need to show information about your overall project status and late tasks on your status report.
What should you do?
In order to communicate the status of your project to your stakeholders, you want to create a real time project status report using Microsoft Excel in Office Online
Services.
You need to show information about your overall project status and late tasks on your status report.
What should you do?
- AFrom the Report tab in Project Pro for Office 365, select the In Progress | Late Tasks report. Save the report as a .pdf file to the designated reports library in PWA.
- BFrom the Project Details view in PWA, change the filter to the Late Tasks filter and copy and paste the tasks into Excel. Save to the designated reports library in PWA.
- CFrom the English folder in the PWA Data Connections library, open the OData Task Data .odc data connection file.
- DFrom the Power Query tab in Excel, select the From other sources | From ODBC option to add data to the report.
Correct Answer:
C
C
send
light_mode
delete
Question #14
DRAG DROP -
You are the Microsoft PPM administrator for a large organization.
You need to ensure that line managers can delegate timesheet approvals to their team members.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.
Select and Place:

You are the Microsoft PPM administrator for a large organization.
You need to ensure that line managers can delegate timesheet approvals to their team members.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.
Select and Place:

send
light_mode
delete
Question #15
The SharePoint Farm administrator for a company installs Microsoft PPM and grants you administrative rights for PWA. The PWA instance is accessible at the
URL: https://AppServer/Live.
You determine that the client needs to implement a Resource Breakdown Structure (RBS) to provide access to projects.
You need to ensure that the RBS is implemented.
What should you do first?
URL: https://AppServer/Live.
You determine that the client needs to implement a Resource Breakdown Structure (RBS) to provide access to projects.
You need to ensure that the RBS is implemented.
What should you do first?
- ARun the Set-SPProjectPermissionMode Windows PowerShell cmdlet.
- BAsk the SharePoint administrator to run the Set-SPProjectPermissionMode Windows PowerShell cmdlet.
- CFrom Settings, select Manage Groups.
- DFrom Site Settings, activate the Project Web App Connectivity feature.
Correct Answer:
B