Question #6
You are a project manager using Microsoft PPM.
You need to create a new project that uses one of your companys templates.
What are two ways to achieve the goal? Each correct answer presents a complete solution.
You need to create a new project that uses one of your companys templates.
What are two ways to achieve the goal? Each correct answer presents a complete solution.
- AFrom Microsoft Project, select Enterprise.
- BIn Project Center, select New, and then select the desired enterprise project type.
- CIn Resource Center, select New.
- DFrom Microsoft Project, select Featured.
Correct Answer:
AB
AB
send
light_mode
delete
Question #7
HOTSPOT -
You are evaluating the requirements for creating a new portfolio analysis.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
Hot Area:

You are evaluating the requirements for creating a new portfolio analysis.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
Hot Area:

send
light_mode
delete
Question #8
Your organization is using Microsoft PPM to manage and track all projects.
The Project Management Office (PMO) needs to know which of the projects are aligned to the organizations strategic objectives.
You need to configure Microsoft PPM to use Portfolio Analysis.
Which two activities should you perform? Each correct answer presents part of the solution.
The Project Management Office (PMO) needs to know which of the projects are aligned to the organizations strategic objectives.
You need to configure Microsoft PPM to use Portfolio Analysis.
Which two activities should you perform? Each correct answer presents part of the solution.
- ASet up Project Departments.
- BPrioritize the drivers by specifying the priority value for each driver.
- CConfigure the Full-time Equivalent calculation.
- DDefine business drivers.
Correct Answer:
BD
References:
https://technet.microsoft.com/en-us/library/dn641991.aspx
BD
References:
https://technet.microsoft.com/en-us/library/dn641991.aspx
send
light_mode
delete
Question #9
Your company has had several large projects fail due to cost overruns and the lack of available resources. These projects use an enterprise project type named
Large IT Project and use a workflow to govern the approval of the projects. The workflow consists of four phases: Initiate, Plan, Execute, and Close.
You need to use Microsoft PPM to compare the value that a new project provides with the cost of implementing the project.
Which three configuration changes should you make? Each correct answer presents part of the solution.
Large IT Project and use a workflow to govern the approval of the projects. The workflow consists of four phases: Initiate, Plan, Execute, and Close.
You need to use Microsoft PPM to compare the value that a new project provides with the cost of implementing the project.
Which three configuration changes should you make? Each correct answer presents part of the solution.
- ANavigate to PWA Settings. Edit the Large IT Project project type, and in the Available Project Detail Page section, add the Strategic Impact form.
- BCreate a project-level custom field that will be used to enter the total cost of a project.
- CDefine your company’s strategic drivers, and enter them into the Strategic Impact form.
- DCreate a project-level custom field that will be used to enter the value statements of why this project should be undertaken.
- EDefine your company’s strategic drivers and enter them into the driver library.
- FIn PWA Settings, edit and then save the stage information. In the Available Project Detail Page section, add the Strategic Impact form.
Correct Answer:
ABE
ABE
send
light_mode
delete
Question #10
You are a portfolio manager for an organization that uses Microsoft PPM to manage projects. You plan to implement Power BI.
You need to import into Power BI by using the Microsoft Project Online content pack.
What should you do?
You need to import into Power BI by using the Microsoft Project Online content pack.
What should you do?
- AIn the Power BI Add content pack library, connect to Microsoft PPM by using the URL for the organization.
- BIn the Power BI Services content pack library, connect to Microsoft PPM using the Microsoft PPM URL for the organization.
- CIn the Power BI Import or Connect to Data tool, select Databases and more. Then, connect to Microsoft PPM by using the database alias for the organization.
- DIn the Power BI My Organization content pack library, connect to Microsoft PPM by using the PWA URL for the organization.
Correct Answer:
B
References:
https://powerbi.microsoft.com/en-us/documentation/powerbi-content-pack-project-online/
B
References:
https://powerbi.microsoft.com/en-us/documentation/powerbi-content-pack-project-online/