Question #1
You are a project manager in an organization that uses Microsoft PPM. You create a proposal for a new project by entering values for the Name, Description,
Proposed Cost, Proposed Benefits, and Sponsor Name properties.
The PMO must be able to approve all project proposals that have a proposed cost above a certain threshold value.
You need to use a project approval workflow.
Which three objects should use? Each correct answer presents part of the solution.
Proposed Cost, Proposed Benefits, and Sponsor Name properties.
The PMO must be able to approve all project proposals that have a proposed cost above a certain threshold value.
You need to use a project approval workflow.
Which three objects should use? Each correct answer presents part of the solution.
- AProject Departments
- BEnterprise Project types
- CProject Detail Pages
- DProject schedule templates
- EPhases and stages
Correct Answer:
BCE
BCE
send
light_mode
delete
Question #2
You use Microsoft PPM to manage an e-commerce portal development program.
The program is separated into individual projects that represent each area of development. This allows each group to manage its own tasks while still having progress visibility at the program level.
You need to be able to see all programs and their associated individual projects from within Project Center.
What should you do?
The program is separated into individual projects that represent each area of development. This allows each group to manage its own tasks while still having progress visibility at the program level.
You need to be able to see all programs and their associated individual projects from within Project Center.
What should you do?
- ASelect the Enterprise Project Type Name field as the value for grouping.
- BSelect the Master Program field as the value for filtering.
- CSelect the Subprojects check box.
- DSelect the Project Details view.
Correct Answer:
C
C
send
light_mode
delete
Question #3
You are the Microsoft PPM administrator for a large company. The IT manager uses four business drivers for prioritization. The priority of all four drivers is set at
25 percent.
The IT manager adds an additional business driver that has a priority value set to 30 percent.
You need to create a new prioritization that includes the additional business driver.
What should you do?
25 percent.
The IT manager adds an additional business driver that has a priority value set to 30 percent.
You need to create a new prioritization that includes the additional business driver.
What should you do?
- ACreate a new calculated prioritization. Select the drivers to prioritize.
- BCreate a new manual prioritization. Select the correct department, and then select the drivers to prioritize.
- CCreate a new manual prioritization. Select the drivers to prioritize, enter the value for each driver, and then choose to normalize.
- DCreate a new manual prioritization. Select the drivers to prioritize, and then rank the drivers sequentially.
Correct Answer:
C
References:
http://deltabahn.com/ppm-driver-prioritization/
C
References:
http://deltabahn.com/ppm-driver-prioritization/
send
light_mode
delete
Question #4
You are using Microsoft PPM to manage an e-commerce portal development program. The program is separated into individual projects that represent each area of development.
You have the following requirements:
✑ All work and progress on individual projects must be reflected in the e-commerce portal development program.
Each group must be able to manage their own tasks.

You need to set up the e-commerce portal development program and its associated projects in Microsoft PPM.
Where should you add resources?
You have the following requirements:
✑ All work and progress on individual projects must be reflected in the e-commerce portal development program.
Each group must be able to manage their own tasks.

You need to set up the e-commerce portal development program and its associated projects in Microsoft PPM.
Where should you add resources?
- Ain the e-commerce portal development program project site
- Bin the individual project schedules
- Cin Build Team, in the e-commerce portal development program schedule
- Din the individual project sites
Correct Answer:
C
C
send
light_mode
delete
Question #5
Your organization is using Microsoft PPM to manage large projects. Within the Microsoft PPM environment, you use SharePoint sites with task lists to manage smaller projects. You turn on the Timesheets feature.
You must collect information about the time that resources spend on all projects.
You need to ensure that you can capture timesheet data from the existing SharePoint task lists.
Which two actions will achieve the goal? Each correct answer presents a complete solution.
You must collect information about the time that resources spend on all projects.
You need to ensure that you can capture timesheet data from the existing SharePoint task lists.
Which two actions will achieve the goal? Each correct answer presents a complete solution.
- AConvert the SharePoint task lists into an enterprise project.
- BUse the Get Started with Project Web App web part to add existing SharePoint task lists to Project Center.
- CActivate the enterprise project features for the SharePoint sites.
- DIn Project Center, add existing SharePoint task lists to PWA as a project.
- EIn SharePoint, add existing SharePoint task lists to Project Center.
Correct Answer:
AC
AC