A customer has the following requirements for an HPE Synergy solution:
✑ Data for the internal application needs to be stored in the frame.
✑ Compute modules need to have access to a large database on an external storage array.
✑ The Synergy infrastructure should be managed with HPE OneView.
How should a Synergy integrator configure the module installation?
A
two SAS Connection Modules into bays 1 and 2; two Synergy 40Gb F8 switch module into bays 3 and 4; two Brocade 16 Gb/12 Fibre Channel switches into bays 5 and 6
B
two SAS Connection Modules into bays 1 and 4; two HPE Synergy Virtual Connect SE 40Gb F8 modules into bays 3 and 6
C
two SAS Connection Modules into bays 1 and 2; two HPE Synergy Virtual Connect SE 40Gb F8 modules into bays 3 and 4
D
two SAS Connection Modules into bays 1 and 4; two Synergy 40Gb F8 switch module into bays 2 and 5; two Brocade 16 Gb/12 Fibre Channel switches into bays 3 and 6