Question #1
A customer has a multi-frame Synergy solution. The customer's Support team recently missed some important alerts in its Composer interface because each pair of Composers resides on a separate management network.
What should the customer do to minimize the risk of this reoccurring?
What should the customer do to minimize the risk of this reoccurring?
- AConfigure HPE Intelligent Management Center.
- BImplement HPE Synergy Global Dashboard.
- CConfigure Remote Support.
- DImplement HPE Systems Insight Manager.
Correct Answer:
B
Reference:
https://support.hpe.com/hpsc/doc/public/display?docId=emr_na-c05061206&docLocale=en_US
B
Reference:
https://support.hpe.com/hpsc/doc/public/display?docId=emr_na-c05061206&docLocale=en_US
send
light_mode
delete
Question #2
DRAG DROP -
A customer needs a Synergy solution configuration with 40Gb uplinks that will connect to network equipment in a different rack.
Click and drag the cable type on the left to the corresponding distance between the frame and the network equipment on the right to meet the customer's needs.
Select and Place:

A customer needs a Synergy solution configuration with 40Gb uplinks that will connect to network equipment in a different rack.
Click and drag the cable type on the left to the corresponding distance between the frame and the network equipment on the right to meet the customer's needs.
Select and Place:

send
light_mode
delete
Question #3
A customer's Synergy solution configuration needs redundant paths to the drives used in the HPE Synergy D3940 storage module.
Which component must be redundant to meet the customer's requirement?
Which component must be redundant to meet the customer's requirement?
- AHPE Synergy 12Gb SAS Connection Module
- BHPE Synergy D3940 storage module
- CHPE Smart Storage Battery with 260mm Cable Kit
- DHPE Compute Module Smart Array P542D SAS Cable
Correct Answer:
A
A
send
light_mode
delete
Question #4
A customer has HPE Synergy SY 480 compute modules with two CPUs and 384GB (16GB DIMMS) of memory. The customer needs to double the CPU and memory capacity for a Java application server.
What should a Synergy integrator do to meet the customer's need?
What should a Synergy integrator do to meet the customer's need?
- AInstall an HPE Synergy SY 620 compute module and reassign the server profile.
- BUpgrade the HPE Synergy SY 480 to two additional CPUs and replace 16Gb dims with 64Gb.
- CInstall an HPE Synergy SY 680 compute module and reassign the server profile.
- DUpgrade the HPE Synergy SY 480 to two additional CPUs and replace 16Gb dims with 32Gb.
Correct Answer:
C
C
send
light_mode
delete
Question #5
Refer to the exhibit.

A customer with the configuration shown attempts to configure a server profile for a new application that requires 20Gb of bandwidth, but the configuration fails.
The HPE SY 480 Gen9 compute modules have two Intel Xeon E5 "" 2695 v4 processors. 256GB of RAM and HPE Synergy 3520C Converged Network Adapters installed.
What is the likely cause of the configuration failure?

A customer with the configuration shown attempts to configure a server profile for a new application that requires 20Gb of bandwidth, but the configuration fails.
The HPE SY 480 Gen9 compute modules have two Intel Xeon E5 "" 2695 v4 processors. 256GB of RAM and HPE Synergy 3520C Converged Network Adapters installed.
What is the likely cause of the configuration failure?
- AHPE Virtual Connect SE 40Gb F8 Module does not support 20Gb.
- BIntel Processor does not have enough PCI-e lanes for 20Gb.
- CHPE 10Gb Interconnect Link Module does not support 20Gb.
- DConverged Network Adapter is unable to support 20Gb.
Correct Answer:
C