Question #41
A product owner asks a newly formed scrum team how many story points will be completed in a sprint.
What should the scrum master do?
What should the scrum master do?
- AEngage the team to determine the sprint velocity based on previous agile projects
- BAverage the sprint velocity based on input from team membersMost Voted
- CShare the sprint velocity obtained from the sponsor with the team
- DRun multiple sprints before determining the sprint velocity with the team
Correct Answer:
D
D
send
light_mode
delete
Question #42
A development team for a small company experiences long delays between product completion and release for validation and testing. The company is concerned that this will impact its ability to complete in the market place.
What analysis should the team use to understand the issues?
What analysis should the team use to understand the issues?
- ARisk management
- BVariance and trend
- CKano model
- DFishbone-diagramMost Voted
Correct Answer:
D
D
send
light_mode
delete
Question #43
Toward the end of a project, the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected.
What should the product owner do?
What should the product owner do?
- ATerminate the project to cut losses
- BReview possible options and make an informed decision to cut losses based on delivered business valueMost Voted
- CBring in experts to increase the probability of success
- DContinue the project, release the product without the failing feature, and fix the feature in a subsequent release
Correct Answer:
D
D
send
light_mode
delete
Question #44
An agile coach is assigned to help a project team that was recently co-located close to a very popular business. Many team members visit this business during working hours which affects team performance.
What should the agile coach do to mitigate this issue?
What should the agile coach do to mitigate this issue?
- ASpeak with the functional managers and come to an agreement that will resolve the issue
- BExplain to functional managers that too much control will inversely impact team morale
- CMeet with the team to discuss the issue and identify specific actions to reduce or eliminate the issueMost Voted
- DInform the team there will be penalties to anyone who visits that business during working hours
Correct Answer:
C
C
send
light_mode
delete
Question #45
After completing the release plan, the team realizes that the project is very likely to have a negative ROI.
What should the team do?
What should the team do?
- APrioritize the backlog, and remove low-priority stories from the release plan to ensure a positive ROI
- BReplace some team embers to reduce the release costs and minimize a negative ROI
- CPerform a root-cause analysis to remove waste from the delivery process and increase the ROIMost Voted
- DCommunicate the risk of a negative ROI to the stakeholders, and update the release plan
Correct Answer:
A
A
send
light_mode
delete
Question #46
During planning for the next iteration, an agile team identifies most of the story points that are expected to be delivered.
How should an agile practitioner work with the team to help identify the iteration's remaining scope?
How should an agile practitioner work with the team to help identify the iteration's remaining scope?
- AConvince the team to stop planning and keep the size small
- BIdentify the technically minimal and achievable tasks
- CRefer to the remaining prioritized backlog itemsMost Voted
- DSelect some of the smallest items from the backlog
Correct Answer:
C
C
send
light_mode
delete
Question #47
During a project meeting, a team is faced with a difficult decision. After discussion and deliberation, the project leader makes the final decision and ends the discussion. This causes a team member to withdraw from future collaboration.
How could the project leader have avoided this?
How could the project leader have avoided this?
- ALed by example by encouraging the team to engage in consensus-driven decision makingMost Voted
- BIterated the need for agile teams to make quick decisions, then followed up with that team member
- CEmpowered a team member to facilitate decision making, then made a final decision on behalf of the team
- DRefrained from participating in the team's decision-making process, except to document and communicate results
Correct Answer:
A
A
send
light_mode
delete
Question #48
During sprint planning the product owner wants the team to prioritize and deliver a number of features which have the highest business value. Due to technical dependencies, the team does not agree with the prioritization.
What should the project leader do?
What should the project leader do?
- AEncourage the product owner and team to reprioritize the features and select ones which can be delivered without any dependencies
- BEncourage the team to continue with the current plan, do what they can, and carry forward the work not done to the next iteration
- CEnsure the team captures the technical dependencies as issues within the backlog optimizationMost Voted
- DEnsure that the required subject matter experts (SMEs) are engaged by the product owner to help with backlog prioritization
Correct Answer:
C
C
send
light_mode
delete
Question #49
During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.
What should the project leader do?
What should the project leader do?
- AFinalize the feedback in the form of a change request
- BLimit the scope of the feedback to only those changes that the team can feasibly accommodate
- CEncourage all feedback, then work with the customer to prioritize work for future sprintsMost Voted
- DAllow the team to decide what feedback to incorporate
Correct Answer:
C
C
send
light_mode
delete
Question #50
An agile team is preparing a release plan for a project.
What information will the team need to complete this plan?
What information will the team need to complete this plan?
- AAmount of work needed to complete a single user story
- BAmount of work that can be accomplished by each team member
- CAmount of work that can be accomplished in an iterationMost Voted
- DAmount of work that can be accomplished by the entire team
Correct Answer:
C
C
send
light_mode
delete