Question #16
Test Management -
You are the Test Manager on a project following an iterative life-cycle model. The project should consist of nine iterations of one month duration each. It is planned to develop the most important features to have a stable core of the application in the first three iterations and to add the additional features in the last six iterations.
At the beginning of the first iteration, only a draft version of the requirements specification document for the core features is available. Assume that during each of the first three iterations, the chosen features are fully completed and unit tested.
Which of the following statements is true in this context?
You are the Test Manager on a project following an iterative life-cycle model. The project should consist of nine iterations of one month duration each. It is planned to develop the most important features to have a stable core of the application in the first three iterations and to add the additional features in the last six iterations.
At the beginning of the first iteration, only a draft version of the requirements specification document for the core features is available. Assume that during each of the first three iterations, the chosen features are fully completed and unit tested.
Which of the following statements is true in this context?
- AThe system test phase should start when all the requirements are frozen
- BYou should allocate a large effort for system testing during the first three iterations
- CYou should allocate all the effort for the system test phase only in the last iteration
- DYou should apply the same test strategy as used in a sequential life cycle model
Correct Answer:
B
B
send
light_mode
delete
Question #17
Test Management -
Which of the following statements, about the test reporting activities for a project adopting an iterative lifecycle model with very short iterations (e.g. two weeks iterations), is correct?
Which of the following statements, about the test reporting activities for a project adopting an iterative lifecycle model with very short iterations (e.g. two weeks iterations), is correct?
- ATest reporting activities can’t be influenced by the use of an iterative lifecycle model with short iterations
- BTest reporting activities are not important for projects adopting an iterative lifecycle model with short iterations
- CTest reporting activities are less important for projects adopting an iterative life cycle model with short iterations. They should be performed at the end of the last iteration
- DTest reporting activities are still important with an iterative lifecycle. The reports can be used to conduct post-iteration review sessions before starting with the next iteration
Correct Answer:
D
D
send
light_mode
delete
Question #18
Test Management -
Consider an agile team adopting Extreme Programming (XP) with five developers and one tester without any coding experience.
To which of the following activities would you expect the tester will contribute most?
Consider an agile team adopting Extreme Programming (XP) with five developers and one tester without any coding experience.
To which of the following activities would you expect the tester will contribute most?
- ADeveloping unit tests
- BExecuting unit tests
- CPlanning and executing tests during the integration test phase to detect interface defects
- DSupporting the customer in the execution of acceptance testing
Correct Answer:
D
D
send
light_mode
delete
Question #19
Test Management -
Which of the following statements best describes an appropriate approach for managing exploratory testing?
Which of the following statements best describes an appropriate approach for managing exploratory testing?
- ADefine very detailed mission statements, which allow testing work to be broken into sessions of up to 10 minutes duration in which testing is guided by these mission statements
- BBreak the testing work in 30 to 120 minutes sessions and use properly defined mission statements consisting of two or three sentences to guide testing during these sessions
- CDefine very generic charters to drive exploratory testing sessions of 2 days where testers are completely free to decide what to test
- DExploratory testing should not be managed because such testing is inherently unmanageable and not measurable
Correct Answer:
B
B
send
light_mode
delete
Question #20
Test Management -
Assume you are managing the system testing phase of a project.
The system test execution period is scheduled to twenty weeks.
All tests are manual tests. You are following a risk-driven test approach.
During the last staff meeting the project manager tells you new deadlines that will not allow completion of all the system tests.
Which of the following would you expect to be the best way to respond to this situation?
Assume you are managing the system testing phase of a project.
The system test execution period is scheduled to twenty weeks.
All tests are manual tests. You are following a risk-driven test approach.
During the last staff meeting the project manager tells you new deadlines that will not allow completion of all the system tests.
Which of the following would you expect to be the best way to respond to this situation?
- APrioritize executing the tests for the highest product risks and track these risks
- BRemove testers from your test team, so that they can be assigned to other projects
- CAutomate all remaining tests
- DNo action is needed, test as much as possible in the remaining time period
Correct Answer:
A
A