Question #21
Which of the following comparisons is true about Scrum and Traditional Project Management?
- AIn Scrum, upfront planning is high, while in Traditional Project Management it is low.
- BIn Scrum, performance measurement is based on plan conformity, while in Traditional Project Management it is based on business value.
- CIn Scrum, customer involvement is high throughput the project, while in Traditional Project it varies according to the project's lifecycle.
- DIn Scrum, Quality Assurance is process centric, while in Traditional Project Management it is customer centric.
Correct Answer:
C
Reference:
http://blog.scrumstudy.com/why-use-scrum-2/
C
Reference:
http://blog.scrumstudy.com/why-use-scrum-2/
send
light_mode
delete
Question #22
Which of the following events does NOT help the Scrum Team in identifying or resolving risks?
- ADaily Standup Meeting
- BSprint Planning Meeting
- CFinancial Planning Meeting
- DPrioritized Product Backlog Review Meeting
Correct Answer:
D
Reference:
http://blog.scrumstudy.com/risk-management-in-scrum/
D
Reference:
http://blog.scrumstudy.com/risk-management-in-scrum/
send
light_mode
delete
Question #23
You are the Scrum Master on a project to develop machine parts for automobile manufacturing. The Product Owner on your project proposes to use Utility
Function to find out the stakeholders' risk tolerance level. Which of the following is NOT a risk tolerance classification?
Function to find out the stakeholders' risk tolerance level. Which of the following is NOT a risk tolerance classification?
- ARisk Averter.
- BRisk Seeker.
- CRisk Mitigator.
- DNeutral Risk Taker.
Correct Answer:
C
Reference:
http://blog.scrumstudy.com/how-to-identify-risk/
C
Reference:
http://blog.scrumstudy.com/how-to-identify-risk/
send
light_mode
delete
Question #24
Change must be integrated properly in the Prioritized Product Backlog. In this regard, which of the following statements is true?
- AIndustry and project types are not determinants of change requirements.
- BChange management is executed in the ongoing processes of prioritizing and adding user stories to the Prioritized Product Backlog.
- CThe type of change is independent of stability or the dynamic nature of a project.
- DOnce changes have been accounted for in the Prioritized Product Backlog, the team need not be concerned about the time and resources available to accomplish the tasks during Sprint.
Correct Answer:
D
Reference:
http://blog.scrumstudy.com/change-management-in-scrum-framework/
D
Reference:
http://blog.scrumstudy.com/change-management-in-scrum-framework/
send
light_mode
delete
Question #25
You are the Scrum Master on a project that is reconstructing the drinking water and sewage system of the city of Bogota. Which of the following characteristics do you NOT need to be?
A) Persuasive -
B) Discerning -
C) Intuitive -
D) Visionary -
A) Persuasive -
B) Discerning -
C) Intuitive -
D) Visionary -