Question #11
DRAG DROP -
A company would like to utilize its current infrastructure but wants to adopt virtualization to consolidate its environment. Currently, the infrastructure contains:
✑ Server with 2 x 8 cores CPUs and 98GB of memory
✑ Backup LAN with a single physical switch
✑ Production LAN
✑ Sufficient datastore performance as determined by the storage team.
Match the existing infrastructure component to its appropriate concept.
Select and Place:

A company would like to utilize its current infrastructure but wants to adopt virtualization to consolidate its environment. Currently, the infrastructure contains:
✑ Server with 2 x 8 cores CPUs and 98GB of memory
✑ Backup LAN with a single physical switch
✑ Production LAN
✑ Sufficient datastore performance as determined by the storage team.
Match the existing infrastructure component to its appropriate concept.
Select and Place:

send
light_mode
delete
Question #12
The system administrator team is planning to upgrade its vCenter Server 5.5 environments to version 6.5.
✑ Each vCenter 5.5 is pointing to a Single Sign On (SSO) server that has a dedicated virtual machine
✑ The SSO servers are currently in independent SSO domains.
✑ During the upgrade process, the administrators would like to combine their two SSO domains into a single one.
View the exhibit.

Referring to the exhibit, which upgrade scenario would accomplish this?
✑ Each vCenter 5.5 is pointing to a Single Sign On (SSO) server that has a dedicated virtual machine
✑ The SSO servers are currently in independent SSO domains.
✑ During the upgrade process, the administrators would like to combine their two SSO domains into a single one.
View the exhibit.

Referring to the exhibit, which upgrade scenario would accomplish this?
- A1. Upgrade the Denver SSP server to a 6.5 PSC. 2. Upgrade the Denver vCenter Server 5.5 to version 6.5. 3. Use the migration utility to upgrade the New York vCenter Server to 6.5. 4. Choose to join it to the Denver PSC.
- B1. Upgrade the Denver SSP server to a 6.5 PSC. 2. Use the migration utility to upgrade the New York SSO server. 3. Choose to join the existing SSO domain during the second upgrade. 4. Upgrade both of the vCenter Servers to 6.5.
- C1. Upgrade both of the SSO Servers to 6.5 PSCs. 2. Upgrade both of the vCenter Servers to 6.5. 3. Install a new 6.5 PSC in the same SSO domain as the Denver 6.5 PSC. 4. Repoint the New York vCenter Server to the newly-installed PSC.
- D1. Install a New York SSO 5.5 server in the same SSO domain as the Denver SSO server. 2. Repoint the New York vCenter Server to the newly-installed SSO server. 3. Upgrade both of the SSO Servers to 6.5 PSCs. 4. Upgrade both of the vCenter Servers to 6.5.
Correct Answer:
B
B
send
light_mode
delete
Question #13
An organization's security policy requires a design where the ESXi hosts will be manageable only through vCenter Server.
Which two security configurations will help meet this requirement? (Choose two.)
Which two security configurations will help meet this requirement? (Choose two.)
- Aenable lockdown mode strict
- Bdisable DCUI access
- Cenable lockdown mode normal
- Ddisable shell access
Correct Answer:
BC
BC
send
light_mode
delete
Question #14
A company is in the process of deploying a modern video-streaming application.
✑ The application is able to scale (expand and collapse) its streaming nodes in the form of CentOS 7.x 64bit virtual machines, based on demand.
✑ This IO-Intensive application has a high CPU demand and generates a significant number of disk operations (IOPS).
✑ To host the application, the company decided to implement a brand-new VMware cluster with vSphere 6.x.
✑ The company would like a significant reduction in CPU utilization as well as possible increase in throughput.
Which virtual disk adapter should be recommended for the company's physical design?
✑ The application is able to scale (expand and collapse) its streaming nodes in the form of CentOS 7.x 64bit virtual machines, based on demand.
✑ This IO-Intensive application has a high CPU demand and generates a significant number of disk operations (IOPS).
✑ To host the application, the company decided to implement a brand-new VMware cluster with vSphere 6.x.
✑ The company would like a significant reduction in CPU utilization as well as possible increase in throughput.
Which virtual disk adapter should be recommended for the company's physical design?
- ALSI Logical Parallel
- BVMware Paravirtual
- CBusLogic Parallel
- DLSI Logic SAS
Correct Answer:
B
Reference -
http://virtuallyhyper.com/2012/09/vcap5-dcd-objective-3-5-determine-virtual-machine-configuration-for-a-vsphere-5-physical-design/
B
Reference -
http://virtuallyhyper.com/2012/09/vcap5-dcd-objective-3-5-determine-virtual-machine-configuration-for-a-vsphere-5-physical-design/
send
light_mode
delete
Question #15
A solution architect has been tasked with designing a new environment for a company's growing needs, and has obtained this information:
✑ Uptime is critical during regular business hours when 95% of the transactions occur. Application uptime must be 99.9% during those hours.
✑ In a true disaster, the business can withstand a day of data loss and half a day of downtime.
✑ The company is one year into a 5-year contact with the co-lo data center.
✑ The building that is currently occupied no longer has any floor space available, but the company has 3 empty racks of space. The co-lo can provide up to
11KVA of power per rack.
✑ There are current contains with Dell to provide servers and with Cisco to provide the network components
✑ The network team has standardized on an end-to-end 10Gb network.
Based on this information, what are two requirements for the new design? (Choose two.)
✑ Uptime is critical during regular business hours when 95% of the transactions occur. Application uptime must be 99.9% during those hours.
✑ In a true disaster, the business can withstand a day of data loss and half a day of downtime.
✑ The company is one year into a 5-year contact with the co-lo data center.
✑ The building that is currently occupied no longer has any floor space available, but the company has 3 empty racks of space. The co-lo can provide up to
11KVA of power per rack.
✑ There are current contains with Dell to provide servers and with Cisco to provide the network components
✑ The network team has standardized on an end-to-end 10Gb network.
Based on this information, what are two requirements for the new design? (Choose two.)
- ARTO of 24 hours.
- BRTO of 12 hours.
- CThe application must be available 99,9% during business hours.
- D11 KVA of power is available per rack.
Correct Answer:
AC