Question #11
Scenario: Vittronics Ltd.
Vittronics Ltd. is a leading medical device manufacturer in the highly competitive market for Migraine Headache Pain Management (MHPM) devices. These tiny wireless devices are implanted in the brain and can deliver a precise electric shock when the wearable Pain Control Unit (PCU) detects an increase in stress induced by the onset of a migraine headache.
This technology will be a breakthrough in the treatment of this condition, and several competitors are striving to be the first to introduce a product into the market.
However, all of them must demonstrate the effectiveness and safety of their products in a set of clinical trials that will satisfy the regulatory requirements of the countries in the target markets.
The Enterprise Architecture group at Vittronics has been engaged in an architecture development project to create a Secure Private Immersive Collaborative
Environment (SPICE) that will allow researchers at its product development laboratories worldwide to share information about their independent clinical trials.
The Vittronics Enterprise Architecture group is a mature organization that has been utilizing TOGAF for several years. They have recently upgraded to TOGAF 9.
The Vittronics Architecture Development Method (VADM) is strictly based on the TOGAF 9 Architecture Development Method (ADM) with extensions required to support current good manufacturing practices and good laboratory practices in their target markets.
The SPICE project team has now completed the Business, Information Systems, and Technology Architecture phases and has produced a complete set of deliverables for each phase. Due to the highly sensitive nature of the information that is managed in SPICE, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant for each domain. A corresponding SPICE Security Architecture has been defined.
The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity. He has stated that the changes to the SPICE architecture will need to be rolled out on a geographic basis that will minimize disruptions to ongoing clinical trials. The work will need to be done in stages and rolled out in geographical regions.
You are serving as the Lead Architect for the SPICE project team.
You have been asked to recommend the approach to identify the work packages that will be included in the Transition Architecture(s).
Based en TOGAF 9, which of the following is the best answer?
Vittronics Ltd. is a leading medical device manufacturer in the highly competitive market for Migraine Headache Pain Management (MHPM) devices. These tiny wireless devices are implanted in the brain and can deliver a precise electric shock when the wearable Pain Control Unit (PCU) detects an increase in stress induced by the onset of a migraine headache.
This technology will be a breakthrough in the treatment of this condition, and several competitors are striving to be the first to introduce a product into the market.
However, all of them must demonstrate the effectiveness and safety of their products in a set of clinical trials that will satisfy the regulatory requirements of the countries in the target markets.
The Enterprise Architecture group at Vittronics has been engaged in an architecture development project to create a Secure Private Immersive Collaborative
Environment (SPICE) that will allow researchers at its product development laboratories worldwide to share information about their independent clinical trials.
The Vittronics Enterprise Architecture group is a mature organization that has been utilizing TOGAF for several years. They have recently upgraded to TOGAF 9.
The Vittronics Architecture Development Method (VADM) is strictly based on the TOGAF 9 Architecture Development Method (ADM) with extensions required to support current good manufacturing practices and good laboratory practices in their target markets.
The SPICE project team has now completed the Business, Information Systems, and Technology Architecture phases and has produced a complete set of deliverables for each phase. Due to the highly sensitive nature of the information that is managed in SPICE, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant for each domain. A corresponding SPICE Security Architecture has been defined.
The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity. He has stated that the changes to the SPICE architecture will need to be rolled out on a geographic basis that will minimize disruptions to ongoing clinical trials. The work will need to be done in stages and rolled out in geographical regions.
You are serving as the Lead Architect for the SPICE project team.
You have been asked to recommend the approach to identify the work packages that will be included in the Transition Architecture(s).
Based en TOGAF 9, which of the following is the best answer?
- ACreate an Implementation Factor Assessment and Deduction Matrix and a Consolidated Gaps, Solutions and Dependencies Matrix. For each gap, identify a proposed solution and classify it as new development, purchased solution, or based on an existing product. Group similar solutions together to form work packages. Identify dependencies between work packages factoring in the clinical trial schedules. Regroup the packages into a set of Capability Increments scheduled into a series of Transition Architectures and documented in an Architecture Definition Increments Table.Most Voted
- BDetermine the set of Solution Building Blocks required by identifying which Solution Building Blocks need to be developed and which need to be procured. Eliminate any duplicate building blocks. Group the remaining Solution Building Blocks together to create the work packages using a CRLO matrix. Rank the work packages in terms of cost and select the most cost-effective options for inclusion in a series of Transition Architectures. Schedule the roll out of the work packages to be sequential across the geographic regions.
- CUse a Consolidated Gaps, Solutions and Dependencies Matrix as a planning tool. For each gap classify whether the solution is either a new development, purchased solution, or based on an existing product. Group the similar solutions together to define the work packages. Regroup the work packages into a set of Capability Increments to transition to the Target Architecture taking into account the schedule for clinical trials.
- DGroup the Solution Building Blocks from a Consolidated Gaps, Solutions and Dependencies Matrix into a set of work packages. Using the matrix as a planning tool, regroup the work packages to account for dependencies. Sequence the work packages into the Capability Increments needed to achieve the Target Architecture. Schedule the rollout one region at a time. Document the progression of the enterprise architecture using an Enterprise Architecture State Evolution table.
Correct Answer:
A
A
send
light_mode
delete
Question #12
Worldwide Mobile is a mobile telecommunications company formed through a series of mergers and acquisitions. They are yet to fully integrate the customer service systems for the most recent acquisitions, and as result, customer service has been a major concern for the Chief Technology Officer.
Results for the last two quarters have shown that Average Revenue Per User (ARPU) and the customer retention (Churn) rate have fallen below the industry average. The Corporate Marketing group has published some new finding about customer satisfaction. The customers appear to be switching to Air Light, a competitor, because of superior customer service. WorldwideMobile actually has better coverage in nearly all markets than Air Light, and good roaming agreement that keep rates low for business travellers. But customer satisfaction has remained low.
The Business Strategy group and the Enterprise Architecture group have conducted a high-level project to develop the enterprise-wide strategic plan. They have developed a business scenario which contains a good conceptual model of what needs to be done and also identifies the key requirements. This was used in preparing the proposal presented to the Executive Council and the Corporate Board.
The planning for the program has been underway for several months. WorldwideMobile has selected TOGAF 9 as the basis for its Enterprise Architecture.
The Corporate Board has approved funding for a multi-million Euro conversion to transition to a packaged Customer Service System. It is anticipated that the overall program will take five years to complete, but there are some tactical projects that can commence immediately to address the situation. The Executive
Council has stated that the program should define specific initiatives to enable each regional business units to create an implementation of the Customer Service
System. The implementation must meet the needs of the business unit and still provide the information needed to enable major improvements to the customer.
You are serving as the Lead Architect for the Performance and Integrity project of the Customer Service System program.
The project has been chartered to address the architecture(s) required to support the Customer Service System from an infrastructure perspective. At present time, the project team is conducting an architecture development project that is focused on the customer self service capability, which was defined as part of the earlier strategic planning activities. This capability will enable customers to access their accounts, pay bills, request account reviews, and provision services from any web-enabled device.
The project team has gathered information about the self-service capability, developed a business scenario, and used the results to define an Architecture Vision for achieving the capability.
You have been asked to recommend the course of action to complete the project.
Based on TOGAF 9, which of the following is best answer?
Results for the last two quarters have shown that Average Revenue Per User (ARPU) and the customer retention (Churn) rate have fallen below the industry average. The Corporate Marketing group has published some new finding about customer satisfaction. The customers appear to be switching to Air Light, a competitor, because of superior customer service. WorldwideMobile actually has better coverage in nearly all markets than Air Light, and good roaming agreement that keep rates low for business travellers. But customer satisfaction has remained low.
The Business Strategy group and the Enterprise Architecture group have conducted a high-level project to develop the enterprise-wide strategic plan. They have developed a business scenario which contains a good conceptual model of what needs to be done and also identifies the key requirements. This was used in preparing the proposal presented to the Executive Council and the Corporate Board.
The planning for the program has been underway for several months. WorldwideMobile has selected TOGAF 9 as the basis for its Enterprise Architecture.
The Corporate Board has approved funding for a multi-million Euro conversion to transition to a packaged Customer Service System. It is anticipated that the overall program will take five years to complete, but there are some tactical projects that can commence immediately to address the situation. The Executive
Council has stated that the program should define specific initiatives to enable each regional business units to create an implementation of the Customer Service
System. The implementation must meet the needs of the business unit and still provide the information needed to enable major improvements to the customer.
You are serving as the Lead Architect for the Performance and Integrity project of the Customer Service System program.
The project has been chartered to address the architecture(s) required to support the Customer Service System from an infrastructure perspective. At present time, the project team is conducting an architecture development project that is focused on the customer self service capability, which was defined as part of the earlier strategic planning activities. This capability will enable customers to access their accounts, pay bills, request account reviews, and provision services from any web-enabled device.
The project team has gathered information about the self-service capability, developed a business scenario, and used the results to define an Architecture Vision for achieving the capability.
You have been asked to recommend the course of action to complete the project.
Based on TOGAF 9, which of the following is best answer?
- AIn the remaining architecture definition phases, the project team should map out the capability in the Technology domain. In the Phases E and F, the capability should be broken down into a set of Solution Building Blocks that define the Target Architecture. Where possible, the Solution Building Blocks should be drawn from the Architecture Repository. The completed Architecture Definition Document and the Implementation and Migration Plan will be submitted for approval. Upon approval, the architecture team will conduct Compliance Assessments to ensure that the Target Architecture is properly implemented.
- BIn the remaining architecture definition phases, the project team should map out the capability across the Business, Information System and Technology domains. In the Phases E and F, the capability should be broken down into a set of increments that are sequenced into Transition Architectures that will lead to the realization of the Target Architecture. The resulting Solution Building Blocks will then provide the basis for the capability increment solutions. The complete Architecture Definition Document and the Implementation and Migration Plan will be submitted for approval. Upon approval, the architecture team will oversee the implementation process through monitoring Architecture Contracts and by conduction Compliance Assessments.Most Voted
- CIn the remaining architecture definition phases, the project team should map out the capability across the Business, Information System and Technology domains. In the Phases E and F, the capability should be broken down into a set of increments that defines the Target Architecture. The Solution Building Blocks will provide the basis for the capability increment solutions. The complete Architecture Definition Document and the Implementation and Migration Plan will be submitted for approval. Upon approval, the architecture team will oversee the implementation process through monitoring Architecture Contracts and by conducting Compliance Assessments.
- DThe remaining architecture definition work should be focused on mapping out the technology and infrastructure capability in the Technology domain. In Phases E and F, the capability should be broken down into a set of Solution Building Blocks that will be implemented to realize the Target Architecture. The Solution Building Blocks will provide the basis for the completed Architecture Definition Document that will be submitted for approval. Upon approval, the implementation team will conduct Compliance Assessments to ensure that the self-service capability is compliant with the overall Enterprise Architecture.
Correct Answer:
B
B
send
light_mode
delete
Question #13
Scenario: AGEX Inc.
AGEX is a large, global commodities trading company which has been growing rapidly through a series of acquisitions.
Each new business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to "leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, AGEX has begun implementing a single Enterprise Resource Planning (ERP) system to consolidate information from several applications that exist across the lines of business. The Corporate Board is concerned that the new ERP system must be able to manage and safeguard customer information in a manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services offered to clients and trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the ERP implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Review Board to oversee and govern the architecture.
After reviewing the available alternatives, and based on recommendations from the ERP vendor, AGEX has selected TOGAF 9 as the basis for its Enterprise
Architecture program.
The CIO has endorsed this choice with the full support of top management.
You are serving as the Chief Architect.
As part of the process for establishing the Enterprise Architecture department, you have decided to create a set of principles to guide the activities.
You have been asked to recommend the best approach for this work.
Based on TOGAF 9, which of the following is the best answer?
AGEX is a large, global commodities trading company which has been growing rapidly through a series of acquisitions.
Each new business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to "leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, AGEX has begun implementing a single Enterprise Resource Planning (ERP) system to consolidate information from several applications that exist across the lines of business. The Corporate Board is concerned that the new ERP system must be able to manage and safeguard customer information in a manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services offered to clients and trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the ERP implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Review Board to oversee and govern the architecture.
After reviewing the available alternatives, and based on recommendations from the ERP vendor, AGEX has selected TOGAF 9 as the basis for its Enterprise
Architecture program.
The CIO has endorsed this choice with the full support of top management.
You are serving as the Chief Architect.
As part of the process for establishing the Enterprise Architecture department, you have decided to create a set of principles to guide the activities.
You have been asked to recommend the best approach for this work.
Based on TOGAF 9, which of the following is the best answer?
- AYou define a set of principles that support the preferred best practices embodied in the Enterprise Architecture department charter. You publish the principles on the corporate intranet to ensure widespread acceptance and compliance. You then schedule regular periodic Compliance Assessments with individual business units to check that they have made satisfactory progress toward meeting the objectives and conditions embodied in the principles.
- BYou gather information from credible industry sources in the commodities business. Based on that, you assess current trends and apply that to defining a set of principles that embody best practices. You select architecture principles that do not conflict with each other and that should be stable. You ensure that all the principles are realistic and avoid including principles that are obvious.
- CYou examine the mission statements for AGEX and each of its businesses, together with the corporate value statements. Based on that, you define a set of principles and review with the CIO. When developing the principles you ensure that they actively promote the alignment of IT with the business strategies and initiatives of AGEX. You then seek the endorsement of the CIO and senior management.
- DYou examine the mission statements for AGEX and each of its businesses, together with the corporate value statements. Based on that, you work with the Architecture Review Board to define the principles. When developing the principles you ensure that they actively promote the alignment of IT with the AGEX business strategies. You then run a series of reviews with all the relevant stakeholders, including senior management, ensuring their support.Most Voted
Correct Answer:
D
D
send
light_mode
delete
Question #14
Scenario:
Your role is consultant to the Lead Architect within a company that manufactures a variety of small electromechanical devices. The company is organized as independent operational divisions.
The company has a mature Enterprise Architecture practice and uses TOGAF standard for the basis of its architecture framework. In addition to the EA program, the company has a number of management frameworks in use, including business planning, portfolio/project management, and operations management. The EA program is sponsored by the CIO.
Each division has completed the Architecture Definition documentation required to tailor and configure the environment to meet its own specific manufacturing requirements.
The enterprise architects have analyzed the key corporate change attributes and implementation constraints. A consolidated gap analysis has been completed which has identified the gaps across the Business, Data, Application, and Technology domains. Based on the results of the gap analysis, the architects have reviewed the requirements, dependencies and interoperability requirements needed to integrate the new ERP environment into the existing environment. The architects have completed the Business Transformation Readiness Assessment started in Phase A. Based on all of these factors they have produced a risk assessment.
The implementation process is estimated to take four years. Because of the risks posed by the complexity of the current environment, a phased approach is needed to implement the target architectures. The implementation and Migration Plan v0 1, the draft Architecture Roadmap, and the Capability Assessment deliverables are now complete.
You have been asked to recommend the next steps to prepare the final Implementation and Migration Plan.
Based on TOGAF standard, which of the following is the best answer?
Your role is consultant to the Lead Architect within a company that manufactures a variety of small electromechanical devices. The company is organized as independent operational divisions.
The company has a mature Enterprise Architecture practice and uses TOGAF standard for the basis of its architecture framework. In addition to the EA program, the company has a number of management frameworks in use, including business planning, portfolio/project management, and operations management. The EA program is sponsored by the CIO.
Each division has completed the Architecture Definition documentation required to tailor and configure the environment to meet its own specific manufacturing requirements.
The enterprise architects have analyzed the key corporate change attributes and implementation constraints. A consolidated gap analysis has been completed which has identified the gaps across the Business, Data, Application, and Technology domains. Based on the results of the gap analysis, the architects have reviewed the requirements, dependencies and interoperability requirements needed to integrate the new ERP environment into the existing environment. The architects have completed the Business Transformation Readiness Assessment started in Phase A. Based on all of these factors they have produced a risk assessment.
The implementation process is estimated to take four years. Because of the risks posed by the complexity of the current environment, a phased approach is needed to implement the target architectures. The implementation and Migration Plan v0 1, the draft Architecture Roadmap, and the Capability Assessment deliverables are now complete.
You have been asked to recommend the next steps to prepare the final Implementation and Migration Plan.
Based on TOGAF standard, which of the following is the best answer?
- AYou would apply the Business Value Assessment Technique to prioritize the implementation projects and project increments. The assessment should focus on return on investment and performance evaluation criteria that can be used to monitor the progress of the architecture transformation. You would confirm the Transition Architecture phases using an Architecture Definition Increments Table to list the projects. You would then document the lessons learned and generate the final plan.
- BYou would assess how the plan impacts the other frameworks in use in the organization. The plan should be coordinated with the business planning, portfolio/ project management and operations management frameworks. You would then assign a business value to each project, considering available resources and priorities for the projects. Finally, you would generate the Implementation and Migration Plan.Most Voted
- CYou would conduct a series of Compliance Assessments to ensure that the implementation team is implementing the architecture according to the contract. The Compliance Assessment should verify that the implementation team is using the proper development methodology. It should include deployment of monitoring tools and ensure that performance targets are being met. If they are not met, then changes to performance requirements should be identified and updated in the Implementation and Migration Plan.
- DYou would place the strategic Architecture Definition and Transition Architectures under configuration control as part of the ongoing architecture development cycle. This will ensure that the architecture remains relevant and responsive to the needs of the enterprise. You would then produce an Implementation Governance Model to manage the lessons learned prior to finalizing the plan. You recommend that lessons learned be accepted by the Architecture Board as changes to the architecture without review.
Correct Answer:
B
B
send
light_mode
delete
Question #15
Scenario:
You are serving as the Lead Architect for the enterprise architecture team at the prime contractor for the Dreadnought Unmanned Aircraft System program.
Over the course of this contract, the company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems. The decision has been made to consolidate and reduce redundant procurement processes and systems. The CEO has announced that the company will seek to leverage higher volume discounts and lower related IT support costs by instituting a preferred supplier program.
TOGAF 9 Is used for internal Enterprise Architecture activities, with an iterative approach for executing Architecture Development Method (ADM) projects.
At present, there are no particularly useful architectural assets related to this initiative, so all assets need to be acquired and customized or created from scratch.
The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving existing processes or systems.
The architect-re development project has put in place Its Architecture Capability for this project and has started a number of iteration cycles to develop the
Architecture. Some tasks to address concerns related to the Business Architecture have been completed. The next immediate task is to address the Information
Systems Architectures.
The Information Systems Architectures must address stakeholder concerns such as:
1. Which procurement-related business processes are supported by zero, one, or many existing applications?
2. What non-procurement applications will need to be integrated with any new procurement applications?
3. What data will need to be shared?
[Note: You may need to refer to TOGAF 9 Chapter 35 in order to answer this question.]
You have been asked to identify the most appropriate catalogs, matrices, and diagrams for this situation.
Based on TOGAF 9, which of the following is the best answer?
You are serving as the Lead Architect for the enterprise architecture team at the prime contractor for the Dreadnought Unmanned Aircraft System program.
Over the course of this contract, the company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems. The decision has been made to consolidate and reduce redundant procurement processes and systems. The CEO has announced that the company will seek to leverage higher volume discounts and lower related IT support costs by instituting a preferred supplier program.
TOGAF 9 Is used for internal Enterprise Architecture activities, with an iterative approach for executing Architecture Development Method (ADM) projects.
At present, there are no particularly useful architectural assets related to this initiative, so all assets need to be acquired and customized or created from scratch.
The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving existing processes or systems.
The architect-re development project has put in place Its Architecture Capability for this project and has started a number of iteration cycles to develop the
Architecture. Some tasks to address concerns related to the Business Architecture have been completed. The next immediate task is to address the Information
Systems Architectures.
The Information Systems Architectures must address stakeholder concerns such as:
1. Which procurement-related business processes are supported by zero, one, or many existing applications?
2. What non-procurement applications will need to be integrated with any new procurement applications?
3. What data will need to be shared?
[Note: You may need to refer to TOGAF 9 Chapter 35 in order to answer this question.]
You have been asked to identify the most appropriate catalogs, matrices, and diagrams for this situation.
Based on TOGAF 9, which of the following is the best answer?
- Ain the early iterations of Architecture development, you would describe the Baseline Application Architecture with a System/Function matrix, and describe the Baseline Data Architecture using a Data Entity/Data Component catalog. In the later Iterations of the Architecture Definition, you would describe the Target Application Architecture using Application Communication diagrams and an Application Interaction matrix, and describe the Target Data Architecture with a System/Data matrix.
- BIn the early iterations of Architecture development, you would describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix, and describe the Target Data Architecture with a System/Data matrix. In the later iterations of Architecture development, you would describe the Baseline Application Architecture with an Application and User Location diagram and a System/Function matrix, and describe the Baseline Data Architecture with a Data Entity/Data Component catalog.
- CIn the early iterations of Architecture development, you would describe the Target Application Architecture with Application Communication diagrams and an Application Interaction matrix, and describe the Target Data Architecture with a Data Entity/Business Function matrix and a System/Data matrix. In the later iterations of Architecture development, you would describe the Baseline Application Architecture with a System/Function matrix, and describe the Baseline Data Architecture with a Data Entity/Data Component catalog.Most Voted
- DIn the early iterations of Architecture development, you would describe the Baseline Application Architecture with a Technology Portfolio catalog, and describe the Baseline Data Architecture with a Data diagram. In the later iterations of Architecture development, you would describe the Target Application Architecture with a System/Technology matrix, and describe the Target Data Architecture with a Data Dissemination diagram.
Correct Answer:
C
C