Question #6
Adding acceptance criteria to each Product Backlog item is a practice many Scrum Teams find useful. Is it the Product Owner’s responsibility to write all of the acceptance criteria for each Product Backlog Items?
- AYes. the Product Owner is responsible for adding acceptance criteria to Product Backlog items.
- BNo, acceptance criteria should be written by the Developers completing the work.
- CIt depends, the Product Owner is accountable for clearly communicating Product Backlog items but they may delegate the responsibility of writing acceptance criteria to others, or they may do the work themselves.
send
light_mode
delete
Question #7
Given only the information in the following three statements:
Product A has a greater potential market than Product B.
Product A has lower customer satisfaction than Product B.
Product B produces more revenue at the present time.
Which investment strategies should you consider for these two products?
Product A has a greater potential market than Product B.
Product A has lower customer satisfaction than Product B.
Product B produces more revenue at the present time.
Which investment strategies should you consider for these two products?
- AFor Doth products, continually measure the impact of any new investments or marketing
- BInvest in Product A to increase its market share, customer satisfaction, and revenue
- CInvestigate an increase in marketing for Product B to grow its market share
- DAll of the above
send
light_mode
delete
Question #8
Complete this sentence: The more uncertain you are about customer needs or market desires _____________ (Choose two.)
- Athe more likely it is that you should invest in a different product.
- Bthe more important a risk management plan becomes.
- Cthe smaller each release should be.
- Dthe more you should focus on validating customer needs.
send
light_mode
delete
Question #9
The primary accountability of a Product Owner is:
- AWriting user Stories that the Scrum Team can fully understand
- BMaximizing the value of the work that the Scrum Team delivers
- CInterfacing between the Developers and the customers
- DManaging the Product Backlog
send
light_mode
delete
Question #10
Which of the following statements about the Product Backlog are true? (Choose two.)
- AAll Product Backlog items must be expressed as user stones.
- BThe Product Backlog represents the input of all stakeholders and eliminates any need for the Developers to speak to stakeholders.
- CAll Product Backlog items must be identified before the first Sprint begins.
- DThe Product Backlog should be visible to the Scrum Team and stakeholders.
- EThe Product Backlog is ordered by the Product Owner.
- FOnly the Product Owner can place items on the Product Backlog.