Question #6
Before you apply an Electronic Software Update (ESU) to an existing environment, which two methods can be used to maintain proper change control over potentially affected objects? (Choose two.)
- ADownload the executable and evaluate it by using Configuration Assistant.
- BDownload the executable and evaluate it by using Change Assistant and the Impact Analysis tool
- CRun the download executable and then evaluate the changed objects by using the OMW Analysis tool.
- DRun the download executable and then run the Impact Analysis tool in the EnterpriseOne Software Updates application.
- ERun the downloaded executable and then run the compare UBE R96IMPANL.
Correct Answer:
BD
BD
send
light_mode
delete
Question #7
After installing an AIS server, what other important EnterpriseOne server component is needed to complete AIS configuration?
- AE1 HTML server and E1 BSSV server
- BE1 HTML server
- CE1 HTML server and Transaction server
- DE1 BSSV server and Enterprise server
- EE1 BSSV server
Correct Answer:
B
B
send
light_mode
delete
Question #8
Which three statements are true about managing and configuring JDE kernels? (Choose three.)
- AEnabling debug logging on a kernel requires restart of the JDE services on an enterprise server.
- BThe security kernel supports multi-thread processing, and handles multiple data/cache requests at a time.
- CThe configuration setting maxNetProcesses defines the maximum number of jdenet_n processes that are allowed to run simultaneously.
- DThe TCP port number defined in the ServiceNameConnect configuration parameter is used to listen to all incoming JDENET messages.
- EThe JDENET process has the capability to launch a child process called Kernels (jdenet_k) as and when request messages come in from clients or servers.
- FThe Reset Cache operation from the Work With Server (P986116) application affects only the Call Object kernels. No other kernel is impacted.
Correct Answer:
CEF
CEF
send
light_mode
delete
Question #9
The server package build on a Linux enterprise server fails with the following error in the server package build logs.

What should you verify in order to troubleshoot this issue?

What should you verify in order to troubleshoot this issue?
- ACheck the database connectivity between the deployment server and the JAS server.
- BCheck the database connectivity between the deployment server and the enterprise server.
- CCheck the database server name for all data source entries where Data Source Use = DB to ensure that the name (uppercase/lowercase) matches exactly with the actual host name of the database server.
- DCheck the enterprise server name for all data source entries where Data Source Use = SVR to ensure that the name (uppercase/lowercase) matches exactly with the actual host name of the enterprise server.
- ECheck the connectivity between the deployment server and enterprise server host machines by using the ping test or telnet.
Correct Answer:
C
C
send
light_mode
delete
Question #10
Which two statements are true about deploying JDE on OPC by using JDE One-Click Provisioning tools? (Choose two.)
- ADeploying the JDE web servers on Java web servers on Java Cloud Service (JCB) is not supported.
- BDeploying the JDE database on Database Cloud Database Cloud Service (DBCS) is supported.
- CDeploying the JDE database on top of a database server that is running in Compute Cloud Service is not supported.
- DWeb server clustering is supported only by using Oracle Traffic Director and Oracle HTTP Server.
- EAfter provisioning, DNC needs to run Install Plan and Workbench to wire up the provisioned JDE servers.
Correct Answer:
CE
CE