Question #11
DRAG DROP -
A manufacturer uses route operations and job scheduling.
You use a unique calendar for a conveyor line. The company observes a decrease in the number of hours a conveyor line resource is operational due to breakdowns. You must make a temporary change to the number of hours the resource is available.
You need to adjust the efficiency percentage for the conveyor line calendar.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Select and Place:

A manufacturer uses route operations and job scheduling.
You use a unique calendar for a conveyor line. The company observes a decrease in the number of hours a conveyor line resource is operational due to breakdowns. You must make a temporary change to the number of hours the resource is available.
You need to adjust the efficiency percentage for the conveyor line calendar.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Select and Place:

send
light_mode
delete
Question #12
A company produces paints and assembles bicycle frames.
You must account for paint drying time before assembly operations can begin. You need to set up the operation to encompass queue times.
Which two options can you use? Each correct answer presents part of solution.
NOTE: Each correct selection is worth one point.
You must account for paint drying time before assembly operations can begin. You need to set up the operation to encompass queue times.
Which two options can you use? Each correct answer presents part of solution.
NOTE: Each correct selection is worth one point.
- AEnter a value in the queue time after field for the painting operation
- BMake a resource group for each size and color and assign that group to the operation
- CEnter a value in the transit time on the painting operation
- DEnter a value in the queue time before field for the assembly operation
- EBuild capabilities for each resource related to color
Correct Answer:
AD
AD
send
light_mode
delete
Question #13
DRAG DROP -
A company manufactures automobile engines.
You must create product configurations for values that are used in different types of engines. Each value is based on a master valve design. Different gaskets and fittings are used to allow valves to work with different engines.
You need to translate production plans into Dynamics 365 Finance and Operations elements.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Select and Place:

A company manufactures automobile engines.
You must create product configurations for values that are used in different types of engines. Each value is based on a master valve design. Different gaskets and fittings are used to allow valves to work with different engines.
You need to translate production plans into Dynamics 365 Finance and Operations elements.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Select and Place:

send
light_mode
delete
Question #14
You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar.
A machine in the facility is defective and must be closed for repairs for the next two days.
You need to configure the resource calendar to close the resource for production for the next two days.
What should you do?
A machine in the facility is defective and must be closed for repairs for the next two days.
You need to configure the resource calendar to close the resource for production for the next two days.
What should you do?
- ANavigate to the resource group. Change the calendar to closed on the resource group.
- BNavigate to the calendar used for production and close the next two days.
- CNavigate to the resource. Change the calendar to closed on the resource.
- DNavigate to the resource and select Calendar deviations. Set the calendar to closed for the next two days.
Correct Answer:
D
D
send
light_mode
delete
Question #15
A manufacturing company is implementing Dynamics 365 Supply Chain Management. The company uses a standard costing model to value inventory.
During the setup of the system, all areas that impact the standard cost of the item must be configured correctly to calculate a complete standard cost by using routing, Bill of materials (BOM) and overhead burden.
You need to verify that all areas of the system are correctly configured.
Which object does NOT impact the standard cost of manufactured items?
During the setup of the system, all areas that impact the standard cost of the item must be configured correctly to calculate a complete standard cost by using routing, Bill of materials (BOM) and overhead burden.
You need to verify that all areas of the system are correctly configured.
Which object does NOT impact the standard cost of manufactured items?