Question #16
DRAG DROP -
Your IT department uses a custom SharePoint list to capture help desk calls and ticket information. Management asks you to report the mean time to repair
(MTTR) on a weekly basis.
You need to modify the list to capture the data necessary to prepare the report.
What should you do? (To answer, move the four appropriate actions from the list of actions to the answer area and arrange them in the correct order.)
Select and Place:

Your IT department uses a custom SharePoint list to capture help desk calls and ticket information. Management asks you to report the mean time to repair
(MTTR) on a weekly basis.
You need to modify the list to capture the data necessary to prepare the report.
What should you do? (To answer, move the four appropriate actions from the list of actions to the answer area and arrange them in the correct order.)
Select and Place:

Correct Answer:
Note: Mean time to repair (MTTR) is a basic measure of the maintainability of repairable items. It represents the average time required to repair a failed component or device. Expressed mathematically, it is the total corrective maintenance time divided by the total number of corrective maintenance actions during a given period of time. It generally does not include lead time for parts not readily available, or other Administrative or Logistic Downtime (ALDT).

Note: Mean time to repair (MTTR) is a basic measure of the maintainability of repairable items. It represents the average time required to repair a failed component or device. Expressed mathematically, it is the total corrective maintenance time divided by the total number of corrective maintenance actions during a given period of time. It generally does not include lead time for parts not readily available, or other Administrative or Logistic Downtime (ALDT).
send
light_mode
delete
Question #17
Your development team uses Microsoft Visual Studio Team Foundation Server (TFS) 2012 with the Microsoft Framework (MSF) for Capability Maturity Model
Integration (CMMI) template.
You are reviewing outstanding issues with your team and trying to agree on whether you can mark a particular issue as resolved.
You need to determine whether the issue has been resolved.
Which two criteria must the team meet before the issue can be marked as resolved? (Each correct answer presents part of the solution. Choose two.)
Integration (CMMI) template.
You are reviewing outstanding issues with your team and trying to agree on whether you can mark a particular issue as resolved.
You need to determine whether the issue has been resolved.
Which two criteria must the team meet before the issue can be marked as resolved? (Each correct answer presents part of the solution. Choose two.)
- AAll impediments under an issue have been completed.
- BAll user stories under an issue have been completed.
- CStakeholders are satisfied that the issue has been resolved.
- DAll tasks under an issue have been completed.
Correct Answer:
CD
CD
send
light_mode
delete
Question #18
You are using the Microsoft Framework (MSF) for Capability Maturity Model Integration (CMMI) Process Improvement 6.0 process template.
You are the scrum master.
You need to assign product requirements to an iteration.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
You are the scrum master.
You need to assign product requirements to an iteration.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
- ACreate a test harness to confirm that the business requirements are understood.
- BFind the dependencies among the product requirements.
- CPrioritize each of the requirements.
- DCreate a prototype to validate whether or not the requirement can be accomplished.
- EEstimate the cost of each of the requirements.
Correct Answer:
BCE
BCE
send
light_mode
delete
Question #19
You are using the Microsoft Visual Studio Scrum 2.0 process template. You recently finished a sprint.
You need to conduct a retrospective meeting prior to planning the next sprint.
What should you do?
You need to conduct a retrospective meeting prior to planning the next sprint.
What should you do?
- ASelect items from the product backlog for the next sprint.
- BDecompose the product backlog items into a set of tasks.
- CDetermine which items have been finished on the previous day.
- DAnalyze the previous sprint to identify what the team is going to do differently during the next sprint.
Correct Answer:
D
D
send
light_mode
delete
Question #20
Your development team uses Scrum as its process framework.
The business communicates a significant change in direction. The current sprint may become obsolete due to the changes.
You need to determine whether the current sprint should be canceled.
Under what circumstances should you cancel the current sprint?
The business communicates a significant change in direction. The current sprint may become obsolete due to the changes.
You need to determine whether the current sprint should be canceled.
Under what circumstances should you cancel the current sprint?
- ATeam members are not able to complete the tasks that were committed to for the sprint.
- BMajor changes to have doubled the required time to complete the tasks.
- CImpediments cause the tasks to not be completed within the sprint.
- DThe sprint goal becomes obsolete.
Correct Answer:
D
D