Question #31
Neil works as a project manager for SoftTech Inc. He is working with Tom, the COO of his company, on several risks within the project. Tom understands that through qualitative analysis Neil has identified many risks in the project. Tom's concern, however, is that the priority list of these risk events are sorted in "high- risk," "moderate-risk," and "low-risk" as conditions apply within the project. Tom wants to know that is there any other objective on which Neil can make the priority list for project risks. What will be Neil's reply to Tom?
- ARisk may be listed by the responses in the near-term
- BRisks may be listed by categories
- CRisks may be listed by the additional analysis and response
- DRisks may be listed by priority separately for schedule, cost, and performance
Correct Answer:
D
D
send
light_mode
delete
Question #32
In which type of access control do user ID and password system come under?
send
light_mode
delete
Question #33
You and your project team are identifying the risks that may exist within your project. Some of the risks are small risks that won't affect your project much if they happen. What should you do with these identified risk events?
- AThese risks can be accepted.
- BThese risks can be added to a low priority risk watch list.
- CAll risks must have a valid, documented risk response.
- DThese risks can be dismissed.
Correct Answer:
B
B
send
light_mode
delete
Question #34
Your project uses a piece of equipment that if the temperature of the machine goes above 450 degree Fahrenheit the machine will overheat and have to be shut down for 48 hours. Should this machine overheat even once it will delay the project's end date. You work with your project to create a response that should the temperature of the machine reach 430, the machine will be paused for at least an hour to cool it down. The temperature of 430 is called what?
send
light_mode
delete
Question #35
Adrian is the project manager of the NHP Project. In her project there are several work packages that deal with electrical wiring. Rather than to manage the risk internally she has decided to hire a vendor to complete all work packages that deal with the electrical wiring. By removing the risk internally to a licensed electrician Adrian feels more comfortable with project team being safe.
What type of risk response has Adrian used in this example?
What type of risk response has Adrian used in this example?
send
light_mode
delete
Question #36
James work as an IT systems personnel in SoftTech Inc. He performs the following tasks:
Runs regular backups and routine tests of the validity of the backup data.
Performs data restoration from the backups whenever required.
Maintains the retained records in accordance with the established information classification policy.
What is the role played by James in the organization?
Runs regular backups and routine tests of the validity of the backup data.
Performs data restoration from the backups whenever required.
Maintains the retained records in accordance with the established information classification policy.
What is the role played by James in the organization?
send
light_mode
delete
Question #37
Which of the following is an entry in an object's discretionary access control list (DACL) that grants permissions to a user or group?
- AAccess control entry (ACE)
- BDiscretionary access control entry (DACE)
- CAccess control list (ACL)
- DSecurity Identifier (SID)
Correct Answer:
A
A
send
light_mode
delete
Question #38
You are the project manager for your organization. You have identified a risk event you're your organization could manage internally or externally. If you manage the event internally it will cost your project $578,000 and an additional $12,000 per month the solution is in use. A vendor can manage the risk event for you. The vendor will charge $550,000 and $14,500 per month that the solution is in use. How many months will you need to use the solution to pay for the internal solution in comparison to the vendor's solution?
- AApproximately 13 months
- BApproximately 11 months
- CApproximately 15 months
- DApproximately 8 months
Correct Answer:
B
B
send
light_mode
delete
Question #39
Which of the following refers to the ability to ensure that the data is not modified or tampered with?
send
light_mode
delete
Question #40
Management wants you to create a visual diagram of what resources will be utilized in the project deliverables. What type of a chart is management asking you to create?
- AWork breakdown structure
- BResource breakdown structure
- CRACI chart
- DRoles and responsibility matrix
Correct Answer:
B