Question #1
Which of the following criteria on test progress would enable the business to determine a likely go live date?
(i) Number of tests planned versus number of tests executed
(ii) Number of high priority defects outstanding
(iii) The test teams timesheets in order to show how much effort has been devoted to testing
(iv) Number of tests passed and number failed
(v) Number of defects found in each development area
(vi) The rate at which defects are being found
(i) Number of tests planned versus number of tests executed
(ii) Number of high priority defects outstanding
(iii) The test teams timesheets in order to show how much effort has been devoted to testing
(iv) Number of tests passed and number failed
(v) Number of defects found in each development area
(vi) The rate at which defects are being found
send
light_mode
delete
Question #2
As a test analyst you are involved in the early stages of an acceptance test for a Product Data Management system. You are asked to write test designs and test cases based on use cases. An early version of the system is also already available. It is a known fact that on the implementation level many things will change
(including the user-interface). The tests will be carried by end-users with much domain knowledge who have also been involved in the project defining the user requirements and reviewing documentation.
What is the BEST option regarding the level of detail and documentation required for test cases in the project?
(including the user-interface). The tests will be carried by end-users with much domain knowledge who have also been involved in the project defining the user requirements and reviewing documentation.
What is the BEST option regarding the level of detail and documentation required for test cases in the project?
- ADetailed concrete test cases since many re-runs of the tests are expected
- BLogical test cases supported by concrete test cases to allow for traceability and enable future changes
- CConcrete test cases only since the end-users have extensive domain knowledge
- DLogical test cases only since the end-user have extensive domain knowledge and many changes are expected thus reducing testware maintenance effort
Correct Answer:
D
D
send
light_mode
delete
Question #3
As a test analyst you are gathering data to support accurate metrics. Which of the following metrics would be MOST appropriate to use to monitor product quality?
- ADefects found versus defects expected
- BTests run and tests passed
- CTest resources spent versus budget
- DCompliance to entry criteria
- EProduct risks outstanding and new risks introduced
Correct Answer:
ABE
ABE
send
light_mode
delete
Question #4
Which of the following tasks and responsibilities do NOT belong to that of a test analyst in the context of evaluating exit criteria and reporting?
- AThe test analyst should be able to use the reporting tools
- BThe test analyst is responsible for supplying accurate information
- CThe test analyst will contribute to the final report at the end of the testing
- DThe test analyst should write final test reports objectively
Correct Answer:
D
D
send
light_mode
delete
Question #5
What is the MOST important reason why test conditions should be understandable by stakeholders?
- AThey should be able to review the test conditions and provide feedback to the test analyst
- BThey should be able to use them as a basis for designing test cases
- CThey should be able to use them to establish traceability to requirements
- DTest documentation should always be understandable by all stakeholders
Correct Answer:
A